Wind power plant, Illinois
Top Hat Wind power plant, Illinois
Top Hat Wind is a 204 MW wind power plant in Logan County, Illinois, operated by Appalachian Power Co, and it generated 73,628 MWh in 2025 (Forms EIA-860 and EIA-923). By 2025 generation it ranks 3,719th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Top Hat Wind plant run compared with other wind plants?
The Top Hat Wind plant had a capacity factor of 4% in 2025 on 204 MW of net summer capacity, below nearly all of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 15 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Top Hat Wind | 4% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Top Hat Wind plant generating more or less than last year?
Top Hat Wind generated 73,628 MWh in 2025; EIA reports no 2024 total to compare. Only 7 months of 2026 have been reported for this plant.
| Period | MWh |
|---|---|
| 2024 | n/a |
| 2025 | 73,628 |
| 2026 through August | 444,130 |
Monthly generation, Dec 2025 to Jul 2026
| Month | MWh |
|---|---|
| July 2026 | 24,031 |
| June 2026 | 49,252 |
| May 2026 | 56,888 |
| April 2026 | 84,905 |
| March 2026 | 87,167 |
| February 2026 | 64,178 |
| January 2026 | 77,709 |
| December 2025 | 73,628 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Top Hat Wind plant, and when do they retire?
1 operable generator totals 204 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 204 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| TPHAT | Operating | Onshore Wind Turbine | 204 | 2025 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Top Hat Wind plant?
EIA lists no joint owners for Top Hat Wind. Appalachian Power Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Appalachian Power Co charge homes?
Appalachian Power Co, the operator of Top Hat Wind, had an average residential price of 17.16¢ per kWh and an average bill of $186 a month in 2025 in Virginia.
| Measure | Price | Monthly bill | Against Illinois |
|---|---|---|---|
| Appalachian Power Co | 17.16¢ | $186 | other state |
| Illinois average | 17.67¢ | $127 | |
| U.S. average | 17.23¢ | $151 | 2% lower |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Top Hat Wind plant?
Top Hat Wind is in Beason, Logan County, Illinois, at 40.1536° N, 89.2225° W. It sits in the PJM Interconnection, LLC balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Illinois are similar in size?
Illinois has 55 operable wind plants with 8,458 MW of capacity, and Top Hat Wind's 204 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| High Trail Wind Farm LLC | McLean | 211 | 508,689 |
| Grand Ridge Wind Energy Center | LaSalle | 210 | 447,231 |
| Bright Stalk Wind Farm I | McLean | 205 | 726,185 |
| Top Hat Wind | Logan | 204 | 73,628 |
| Sugar Creek Wind One LLC | Logan | 202 | 581,921 |
| Harvest Ridge Wind Farm | Douglas | 202 | 667,048 |
| Alta Farms II Wind Project, LLC | DeWitt | 201 | 545,768 |
Source: EIA Forms EIA-860 and EIA-923, 2025.