Skip to main content
RateWatt

Wind power plant, South Dakota

Triple H Wind Project, South Dakota

Triple H Wind Project is a 250 MW wind power plant in Hyde County, South Dakota, operated by Engie North America, and it generated 1,030,948 MWh in 2025 (Forms EIA-860 and EIA-923). That is 4.7% of the generation reported in South Dakota, and its capacity factor sits at the 95th percentile of U.S. wind plants. By 2025 generation it ranks 721st of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

250 MWNameplate capacity
47%Capacity factor, 2025, 95th percentile, on 250 MW net summer
4.7%Of SD generation, 2025
5 yearsAverage generator age, by MW

How hard does the Triple H Wind Project plant run compared with other wind plants?

The Triple H Wind Project plant had a capacity factor of 47% in 2025 on 250 MW of net summer capacity, the 95th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 172 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Triple H Wind Project47%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Triple H Wind Project plant generating more or less than last year?

Generation at Triple H Wind Project rose 6.5% from 2024 to 2025, from 968,341 MWh to 1,030,948 MWh. Through August 2026 it is running 24.8% behind the same months of 2025.

Net generation by period
PeriodMWh
2024968,341
20251,030,948
2026 through August513,072
2025, same months681,953
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20260
July 20260
June 202674,376
May 202693,405
April 202686,345
March 202696,247
February 202679,952
January 202682,747
December 202593,130
November 202574,877
October 2025113,030
September 202567,958
August 202572,752
July 202575,649
June 202570,600
May 202592,817
April 202599,573
March 202598,742
February 202575,208
January 202596,612
December 202467,491
November 202472,024
October 202497,862
September 2024100,920
August 202484,817
July 202459,065
June 202481,078
May 202478,987
April 202496,360
March 202493,728
February 202473,970
January 202462,039

Source: EIA Form EIA-923, through August 2026.

How much of South Dakota's electricity comes from the Triple H Wind Project plant?

Triple H Wind Project made 4.7% of the 21,865,712 MWh reported by South Dakota plants in 2025, from 3.3% of the state's 7,670 MW of capacity. Its share of output is 1.4 times its share of capacity. By capacity it is the 10th largest of 54 plants in South Dakota, the 1,238th largest of 14,327 in the U.S. and the 138th largest of 1,358 wind plants. By 2025 generation it is the 6th largest of 50 generating plants in the state.

Triple H Wind Project within South Dakota, 2025
MeasureThis plantSouth DakotaShare
Capacity (MW)2507,6703.3%
Generation (MWh)1,030,94821,865,7124.7%
Wind capacity (MW)2503,4577.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Triple H Wind Project plant, and when do they retire?

1 operable generator totals 250 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1250100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
WTGOperatingOnshore Wind Turbine2502020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Triple H Wind Project plant?

Triple H Wind Project, LLC is the only joint owner reported for Triple H Wind Project, with 100.0%. Engie North America operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Triple H Wind Project plant?

Triple H Wind Project is in Highmore, Hyde County, South Dakota, at 44.4010° N, 99.6038° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in South Dakota are similar in size?

South Dakota has 25 operable wind plants with 3,457 MW of capacity, and Triple H Wind Project's 250 MW is 7% of that.

Wind plants in South Dakota around this size
PlantCountyMW2025 MWh
Dakota Range WindGrant3041,016,519
Deuel Harvest Wind Energy LLCDeuel3001,102,411
Triple H Wind ProjectHyde2501,030,948
Prevailing Wind ParkYankton220850,790
Buffalo Ridge II LLCBrookings210479,324
Crowned Ridge Wind II Energy CenterCodington201869,983

Source: EIA Forms EIA-860 and EIA-923, 2025.