Skip to main content
RateWatt

Petroleum power plant, Montana

Yellowstone Energy LP petroleum power plant, Montana

Yellowstone Energy LP is a 68 MW petroleum power plant in Yellowstone County, Montana, operated by Yellowstone Energy LP, and it generated 458,357 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.7% of the generation reported in Montana, and its capacity factor sits at the 99th percentile of U.S. petroleum plants. By 2025 generation it ranks 1,435th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

68 MWNameplate capacity
100%Capacity factor, 2025, 99th percentile, on 52 MW net summer
1.7%Of MT generation, 2025
30 yearsAverage generator age, by MW

How hard does the Yellowstone Energy LP plant run compared with other petroleum plants?

The Yellowstone Energy LP plant had a capacity factor of 100% in 2025 on 52 MW of net summer capacity, the 99th percentile of the 143 U.S. petroleum plants with at least 20 MW. The typical petroleum plant reached 1%. That equals about 365 days at full output out of 365.

0%Shaded: the middle half of petroleum plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Yellowstone Energy LP100%
Petroleum plants, 75th percentile1%
Petroleum plants, median1%
Petroleum plants, 25th percentile0%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Yellowstone Energy LP plant generating more or less than last year?

Generation at Yellowstone Energy LP rose 20.0% from 2024 to 2025, from 381,832 MWh to 458,357 MWh. Through August 2026 it is running 31.8% behind the same months of 2025.

Net generation by period
PeriodMWh
2024381,832
2025458,357
2026 through August223,097
2025, same months327,280
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20265,485
July 20260
June 202613,972
May 202643,471
April 202642,467
March 202643,663
February 202639,449
January 202634,590
December 202535,930
November 202530,208
October 202533,622
September 202531,317
August 202537,281
July 202536,817
June 202541,403
May 202542,350
April 202541,926
March 202543,770
February 202539,550
January 202544,183
December 202442,901
November 202423,035
October 20241,796
September 202431,681
August 202433,831
July 202436,255
June 202439,790
May 202428,931
April 202422,923
March 202443,905
February 202440,011
January 202436,773

Source: EIA Form EIA-923, through August 2026.

How much of Montana's electricity comes from the Yellowstone Energy LP plant?

Yellowstone Energy LP made 1.7% of the 26,725,203 MWh reported by Montana plants in 2025, from 0.9% of the state's 7,662 MW of capacity. Its share of output is 1.9 times its share of capacity. By capacity it is the 28th largest of 73 plants in Montana, the 3,393rd largest of 14,327 in the U.S. and the 73rd largest of 861 petroleum plants. By 2025 generation it is the 13th largest of 71 generating plants in the state.

Yellowstone Energy LP within Montana, 2025
MeasureThis plantMontanaShare
Capacity (MW)687,6620.9%
Generation (MWh)458,35726,725,2031.7%
Petroleum capacity (MW)6868100.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Yellowstone Energy LP plant, and when do they retire?

1 operable generator totals 68 MW, with an average age of 30 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1990s168100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN1OperatingPetroleum Coke681995n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Yellowstone Energy LP plant?

EIA lists no joint owners for Yellowstone Energy LP. Yellowstone Energy LP operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Yellowstone Energy LP plant?

Yellowstone Energy LP is in Billings, Yellowstone County, Montana, at 45.8117° N, 108.4278° W. It sits in the NorthWestern Energy (NWMT) balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which Montana power plants are similar in size?

Yellowstone Energy LP is the only operable petroleum plant in Montana, so these are the plants of any fuel closest to its 68 MW.

Power plants in Montana around this size
PlantFuelCountyMW2025 MWh
MTSUNSolarYellowstone80149,035
Apex SolarSolarBeaverhead80164,724
Stillwater Wind, LLCWindStillwater80252,726
Yellowstone Energy LPPetroleumYellowstone68458,357
MoronyHydroCascade63214,712
CochraneHydroCascade59215,322
Rainbow (MT)HydroCascade59298,642

Source: EIA Forms EIA-860 and EIA-923, 2025.