Appaloosa Solar I power plant, Utah

Appaloosa Solar I is a 200 MW solar power plant in Iron County, Utah, operated by Greenbacker Renewable Energy Corporation, and it generated 539,459 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.4% of the generation reported in Utah, and its capacity factor sits at the 94th percentile of U.S. solar plants. By 2025 generation it ranks 1,267th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

200 MWNameplate capacity
31%Capacity factor, 2025, 94th percentile, on 198 MW net summer
1.4%Of UT generation, 2025
1 yearAverage generator age, by MW

How hard does the Appaloosa Solar I plant run compared with other solar plants?

The Appaloosa Solar I plant had a capacity factor of 31% in 2025 on 198 MW of net summer capacity, the 94th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 114 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Appaloosa Solar I31%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Appaloosa Solar I plant generating more or less than last year?

Generation at Appaloosa Solar I rose 2.4% from 2024 to 2025, from 526,899 MWh to 539,459 MWh. Through August 2026 it is running 34.9% behind the same months of 2025.

Net generation by period
PeriodMWh
2024526,899
2025539,459
2026 through August260,038
2025, same months399,397
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202648,678
July 202619,909
June 202665,836
May 202659,650
April 202654,540
March 20265,048
February 20262,666
January 20263,711
December 202524,523
November 202526,151
October 202541,222
September 202548,166
August 202554,216
July 202562,864
June 202562,983
May 202557,525
April 202552,329
March 202544,033
February 202535,718
January 202529,729
December 202426,067
November 202428,673
October 202439,961
September 202450,606
August 202454,743
July 202459,861
June 202464,506
May 202463,384
April 202454,670
March 202440,144
February 202424,386
January 202419,898

Source: EIA Form EIA-923, through August 2026.

How much of Utah's electricity comes from the Appaloosa Solar I plant?

Appaloosa Solar I made 1.4% of the 38,124,679 MWh reported by Utah plants in 2025, from 1.8% of the state's 11,140 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 11th largest of 126 plants in Utah, the 1,524th largest of 14,327 in the U.S. and the 164th largest of 7,223 solar plants. By 2025 generation it is the 9th largest of 117 generating plants in the state.

Appaloosa Solar I within Utah, 2025
MeasureThis plantUtahShare
Capacity (MW)20011,1401.8%
Generation (MWh)539,45938,124,6791.4%
Solar capacity (MW)2003,0376.6%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Appaloosa Solar I plant, and when do they retire?

2 operable generators total 200 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s2200100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
AS1AOperatingSolar Photovoltaic1202024n/a
AS1BOperatingSolar Photovoltaic802024n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Appaloosa Solar I plant?

EIA lists no joint owners for Appaloosa Solar I. Greenbacker Renewable Energy Corporation operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Appaloosa Solar I plant?

Appaloosa Solar I is in Cedar City, Iron County, Utah, at 37.8402° N, 113.1359° W. It sits in the PacifiCorp - East balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Utah are similar in size?

Utah has 55 operable solar plants with 3,037 MW of capacity, and Appaloosa Solar I's 200 MW is 7% of that.

Solar plants in Utah around this size
PlantCountyMW2025 MWh
Appaloosa Solar IIron200539,459
Hornshadow Solar II, LLCEmery200227,612
Cove Mountain Solar 2Iron122321,393
Hunter Solar LLC (UT)Emery100259,575

Source: EIA Forms EIA-860 and EIA-923, 2025.