Skip to main content
RateWatt

Solar power plant, Utah

Cove Mountain Solar 2 power plant, Utah

Cove Mountain Solar 2 is a 122 MW solar power plant in Iron County, Utah, operated by Cove Mountain Solar 2 LLC, and it generated 321,393 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.8% of the generation reported in Utah, and its capacity factor sits at the 91st percentile of U.S. solar plants. By 2025 generation it ranks 1,874th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

122 MWNameplate capacity
30%Capacity factor, 2025, 91st percentile, on 122 MW net summer
0.8%Of UT generation, 2025
5 yearsAverage generator age, by MW

How hard does the Cove Mountain Solar 2 plant run compared with other solar plants?

The Cove Mountain Solar 2 plant had a capacity factor of 30% in 2025 on 122 MW of net summer capacity, the 91st percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 110 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Cove Mountain Solar 230%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Cove Mountain Solar 2 plant generating more or less than last year?

Generation at Cove Mountain Solar 2 rose 3.9% from 2024 to 2025, from 309,321 MWh to 321,393 MWh. Through August 2026 it is running 4.5% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024309,321
2025321,393
2026 through August247,802
2025, same months237,056
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202633,827
July 202636,465
June 202640,095
May 202637,499
April 202632,887
March 202631,112
February 202619,312
January 202616,605
December 202514,007
November 202515,357
October 202525,074
September 202529,899
August 202532,860
July 202538,058
June 202537,804
May 202534,164
April 202532,303
March 202524,884
February 202520,780
January 202516,203
December 202414,349
November 202415,300
October 202423,669
September 202429,419
August 202431,619
July 202432,525
June 202438,032
May 202437,239
April 202433,506
March 202423,503
February 202416,415
January 202413,745

Source: EIA Form EIA-923, through August 2026.

How much of Utah's electricity comes from the Cove Mountain Solar 2 plant?

Cove Mountain Solar 2 made 0.8% of the 38,124,679 MWh reported by Utah plants in 2025, from 1.1% of the state's 11,140 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 16th largest of 126 plants in Utah, the 2,294th largest of 14,327 in the U.S. and the 374th largest of 7,223 solar plants. By 2025 generation it is the 13th largest of 117 generating plants in the state.

Cove Mountain Solar 2 within Utah, 2025
MeasureThis plantUtahShare
Capacity (MW)12211,1401.1%
Generation (MWh)321,39338,124,6790.8%
Solar capacity (MW)1223,0374.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Cove Mountain Solar 2 plant, and when do they retire?

1 operable generator totals 122 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1122100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN01OperatingSolar Photovoltaic1222020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Cove Mountain Solar 2 plant?

EIA lists no joint owners for Cove Mountain Solar 2. Cove Mountain Solar 2 LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Cove Mountain Solar 2 plant?

Cove Mountain Solar 2 is in Beryl, Iron County, Utah, at 37.6386° N, 113.6371° W. It sits in the PacifiCorp - East balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Utah are similar in size?

Utah has 55 operable solar plants with 3,037 MW of capacity, and Cove Mountain Solar 2's 122 MW is 4% of that.

Solar plants in Utah around this size
PlantCountyMW2025 MWh
Appaloosa Solar IIron200539,459
Hornshadow Solar II, LLCEmery200227,612
Cove Mountain Solar 2Iron122321,393
Hunter Solar LLC (UT)Emery100259,575
Hornshadow Solar, LLCEmery100149,128
Milford Solar 1Beaver99260,650

Source: EIA Forms EIA-860 and EIA-923, 2025.