Borden Solar Farm is a 50 MW solar power plant in Madera County, California, operated by 41MB 8me, LLC, and it generated 113,447 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 71st percentile of U.S. solar plants. By 2025 generation it ranks 3,271st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Borden Solar Farm plant run compared with other solar plants?
The Borden Solar Farm plant had a capacity factor of 26% in 2025 on 50 MW of net summer capacity, the 71st percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 95 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Borden Solar Farm | 26% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Borden Solar Farm plant generating more or less than last year?
Generation at Borden Solar Farm fell 0.4% from 2024 to 2025, from 113,880 MWh to 113,447 MWh. Through August 2026 it is running 41.6% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 113,880 |
| 2025 | 113,447 |
| 2026 through August | 52,718 |
| 2025, same months | 90,245 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 8,901 |
| July 2026 | 7,604 |
| June 2026 | 6,804 |
| May 2026 | 8,461 |
| April 2026 | 6,232 |
| March 2026 | 6,695 |
| February 2026 | 4,470 |
| January 2026 | 3,551 |
| December 2025 | 1,804 |
| November 2025 | 3,228 |
| October 2025 | 6,919 |
| September 2025 | 11,251 |
| August 2025 | 14,534 |
| July 2025 | 15,946 |
| June 2025 | 15,731 |
| May 2025 | 14,979 |
| April 2025 | 12,212 |
| March 2025 | 2,732 |
| February 2025 | 6,881 |
| January 2025 | 7,230 |
| December 2024 | 4,065 |
| November 2024 | 5,917 |
| October 2024 | 9,549 |
| September 2024 | 11,995 |
| August 2024 | 13,308 |
| July 2024 | 12,733 |
| June 2024 | 10,395 |
| May 2024 | 9,543 |
| April 2024 | 13,342 |
| March 2024 | 11,005 |
| February 2024 | 7,148 |
| January 2024 | 4,880 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Borden Solar Farm plant, and when do they retire?
1 operable generator totals 50 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 50 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| BRDN | Operating | Solar Photovoltaic | 50 | 2020 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Borden Solar Farm plant?
EIA lists no joint owners for Borden Solar Farm. 41MB 8me, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Borden Solar Farm plant?
Borden Solar Farm is in Madera, Madera County, California, at 36.9411° N, 119.9600° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Borden Solar Farm's 50 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Solar Star California, XLI, LLC | Kern | 54 | 147,197 |
| Alpaugh 50 | Tulare | 50 | 57,324 |
| Hecate Energy Beacon Solar 4 | Kern | 50 | 115,929 |
| Borden Solar Farm | Madera | 50 | 113,447 |
| Antelope DSR 1 | Los Angeles | 50 | 131,226 |
| Midway Solar Farm 1 | Imperial | 50 | 108,244 |
| Little Bear 4 | Fresno | 50 | 37,480 |
Source: EIA Forms EIA-860 and EIA-923, 2025.