Cactus Flats Wind Energy Project is a 148 MW wind power plant in Concho County, Texas, operated by Southern Power Co, and it generated 439,139 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 53rd percentile of U.S. wind plants. By 2025 generation it ranks 1,488th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

148 MWNameplate capacity
34%Capacity factor, 2025, 53rd percentile, on 148 MW net summer
0.1%Of TX generation, 2025
7 yearsAverage generator age, by MW

How hard does the Cactus Flats Wind Energy Project plant run compared with other wind plants?

The Cactus Flats Wind Energy Project plant had a capacity factor of 34% in 2025 on 148 MW of net summer capacity, the 53rd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 123 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Cactus Flats Wind Energy Project34%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Cactus Flats Wind Energy Project plant generating more or less than last year?

Generation at Cactus Flats Wind Energy Project fell 3.7% from 2024 to 2025, from 455,798 MWh to 439,139 MWh. Through August 2026 it is running 0.2% behind the same months of 2025.

Net generation by period
PeriodMWh
2024455,798
2025439,139
2026 through August309,611
2025, same months310,234
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202638,428
July 202635,879
June 202637,657
May 202636,032
April 202643,353
March 202651,559
February 202636,253
January 202630,450
December 202538,155
November 202526,397
October 202534,187
September 202530,166
August 202526,897
July 202531,395
June 202542,176
May 202536,603
April 202547,060
March 202549,357
February 202539,978
January 202536,768
December 202440,693
November 202449,023
October 202442,926
September 202421,168
August 202432,422
July 202430,653
June 202439,060
May 202438,696
April 202439,633
March 202435,563
February 202449,158
January 202436,803

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Cactus Flats Wind Energy Project plant?

Cactus Flats Wind Energy Project made 0.1% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. By capacity it is the 434th largest of 1,023 plants in Texas, the 2,090th largest of 14,327 in the U.S. and the 494th largest of 1,358 wind plants. By 2025 generation it is the 306th largest of 816 generating plants in the state.

Cactus Flats Wind Energy Project within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)148195,9660.1%
Generation (MWh)439,139592,896,1760.1%
Wind capacity (MW)14843,9420.3%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Cactus Flats Wind Energy Project plant, and when do they retire?

1 operable generator totals 148 MW, with an average age of 7 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s1148100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
WT1OperatingOnshore Wind Turbine1482018n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Cactus Flats Wind Energy Project plant?

SP Cactus Flats Wind Energy, LLC is the only joint owner reported for Cactus Flats Wind Energy Project, with 100.0%. Southern Power Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Cactus Flats Wind Energy Project plant?

Cactus Flats Wind Energy Project is in Eden, Concho County, Texas, at 31.1125° N, 100.0281° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Texas are similar in size?

Texas has 228 operable wind plants with 43,942 MW of capacity, and Cactus Flats Wind Energy Project's 148 MW is 0% of that.

Wind plants in Texas around this size
PlantCountyMW2025 MWh
Goat Wind LPSterling150271,373
RockspringsVal Verde149491,159
Blue Cloud Wind Energy LLCBailey148564,040
Cactus Flats Wind Energy ProjectConcho148439,139
Ranchland Wind Project IICallahan148500,101
Palmas Wind, LLCCameron145362,544
Panther Creek Wind Farm IHoward143529,689

Source: EIA Forms EIA-860 and EIA-923, 2025.