Solar power plant, Illinois
Cass County Renewable Energy Center, Illinois
Cass County Renewable Energy Center is a 150 MW solar power plant in Cass County, Illinois, operated by Union Electric Co-(MO), and it generated 331,772 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Illinois, and its capacity factor sits at the 66th percentile of U.S. solar plants. By 2025 generation it ranks 1,840th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Cass County Renewable Energy Center plant run compared with other solar plants?
The Cass County Renewable Energy Center plant had a capacity factor of 25% in 2025 on 150 MW of net summer capacity, the 66th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 92 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Cass County Renewable Energy Center | 25% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Cass County Renewable Energy Center plant generating more or less than last year?
Cass County Renewable Energy Center generated 331,772 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 11.9% behind the same months of 2025. 2024 has output for only 1 month, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 331 |
| 2025 | 331,772 |
| 2026 through August | 217,103 |
| 2025, same months | 246,400 |
Monthly generation, Dec 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 34,417 |
| July 2026 | 42,748 |
| June 2026 | 33,253 |
| May 2026 | 29,336 |
| April 2026 | 24,944 |
| March 2026 | 11,169 |
| February 2026 | 22,394 |
| January 2026 | 18,842 |
| December 2025 | 12,105 |
| November 2025 | 17,420 |
| October 2025 | 21,359 |
| September 2025 | 34,488 |
| August 2025 | 39,800 |
| July 2025 | 37,465 |
| June 2025 | 36,623 |
| May 2025 | 35,840 |
| April 2025 | 28,483 |
| March 2025 | 30,154 |
| February 2025 | 20,918 |
| January 2025 | 17,117 |
| December 2024 | 331 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Cass County Renewable Energy Center plant, and when do they retire?
1 operable generator totals 150 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 150 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| CCREC | Operating | Solar Photovoltaic | 150 | 2024 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Cass County Renewable Energy Center plant?
EIA lists no joint owners for Cass County Renewable Energy Center. Union Electric Co-(MO) operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Union Electric Co charge homes?
Union Electric Co, the operator of Cass County Renewable Energy Center, had an average residential price of 13.27¢ per kWh and an average bill of $137 a month in 2025 in Missouri.
| Measure | Price | Monthly bill | Against Illinois |
|---|---|---|---|
| Union Electric Co | 13.27¢ | $137 | other state |
| Illinois average | 17.67¢ | $127 | |
| U.S. average | 17.23¢ | $151 | 2% lower |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Cass County Renewable Energy Center plant?
Cass County Renewable Energy Center is in Beardstown, Cass County, Illinois, at 39.9778° N, 90.4711° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Illinois are similar in size?
Illinois has 406 operable solar plants with 4,387 MW of capacity, and Cass County Renewable Energy Center's 150 MW is 3% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| River Ferry Solar 1 | Clark | 165 | 304,116 |
| Eldorado Solar I | Saline | 150 | 308,348 |
| Boomtown Renewable Energy Center | White | 150 | 286,304 |
| Cass County Renewable Energy Center | Cass | 150 | 331,772 |
| Pleasantville Solar Park | Fulton | 150 | 48,205 |
| Tilden Solar | Randolph | 150 | 25,874 |
| Big River Solar | White | 149 | 314,717 |
Source: EIA Forms EIA-860 and EIA-923, 2025.