Desert Sky is a 168 MW wind power plant in Pecos County, Texas, operated by Desert Sky Wind Farm LP, and it generated 541,153 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 63rd percentile of U.S. wind plants. By 2025 generation it ranks 1,265th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Desert Sky plant run compared with other wind plants?
The Desert Sky plant had a capacity factor of 37% in 2025 on 168 MW of net summer capacity, the 63rd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 134 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Desert Sky | 37% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Desert Sky plant generating more or less than last year?
Generation at Desert Sky rose 8.9% from 2024 to 2025, from 496,721 MWh to 541,153 MWh.
| Period | MWh |
|---|---|
| 2024 | 496,721 |
| 2025 | 541,153 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 36,493 |
| November 2025 | 44,046 |
| October 2025 | 48,337 |
| September 2025 | 38,377 |
| August 2025 | 37,550 |
| July 2025 | 49,070 |
| June 2025 | 62,677 |
| May 2025 | 39,304 |
| April 2025 | 58,329 |
| March 2025 | 56,663 |
| February 2025 | 34,047 |
| January 2025 | 36,260 |
| December 2024 | 42,821 |
| November 2024 | 48,437 |
| October 2024 | 50,865 |
| September 2024 | 28,693 |
| August 2024 | 40,122 |
| July 2024 | 36,008 |
| June 2024 | 49,634 |
| May 2024 | 37,109 |
| April 2024 | 48,920 |
| March 2024 | 41,523 |
| February 2024 | 41,108 |
| January 2024 | 31,481 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Desert Sky plant, and when do they retire?
1 operable generator totals 168 MW, with an average age of 23 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 168 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Onshore Wind Turbine | 168 | 2002 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Desert Sky plant?
EIA lists no joint owners for Desert Sky. Desert Sky Wind Farm LP operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Desert Sky plant?
Desert Sky is in Iraan, Pecos County, Texas, at 30.9178° N, 102.0867° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Texas are similar in size?
Texas has 228 operable wind plants with 43,942 MW of capacity, and Desert Sky's 168 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Appaloosa Run Wind | Upton | 172 | 699,112 |
| Buffalo Gap 3 Wind Farm | Nolan | 170 | 337,716 |
| Turkey Track Wind Energy LLC | Nolan | 170 | 331,425 |
| Desert Sky | Pecos | 168 | 541,153 |
| Hart Wind | Castro | 166 | 343,988 |
| Hackberry Wind Farm | Shackelford | 166 | 228,393 |
| Cameron Wind 1 LLC | Cameron | 165 | 350,743 |