Solar power plant, Texas
Ellis Solar LLC power plant, Texas
Ellis Solar LLC is a 80 MW solar power plant in Ellis County, Texas, operated by 174 Power Global Corp., and it generated 165,050 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 54th percentile of U.S. solar plants. By 2025 generation it ranks 2,760th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Ellis Solar LLC plant run compared with other solar plants?
The Ellis Solar LLC plant had a capacity factor of 24% in 2025 on 80 MW of net summer capacity, the 54th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 86 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Ellis Solar LLC | 24% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Ellis Solar LLC plant generating more or less than last year?
Generation at Ellis Solar LLC rose 8.2% from 2024 to 2025, from 152,572 MWh to 165,050 MWh. Through August 2026 it is running 1.1% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 152,572 |
| 2025 | 165,050 |
| 2026 through August | 118,221 |
| 2025, same months | 116,940 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 18,858 |
| July 2026 | 19,378 |
| June 2026 | 17,143 |
| May 2026 | 15,648 |
| April 2026 | 11,389 |
| March 2026 | 14,533 |
| February 2026 | 11,619 |
| January 2026 | 9,653 |
| December 2025 | 8,559 |
| November 2025 | 10,914 |
| October 2025 | 13,956 |
| September 2025 | 14,681 |
| August 2025 | 16,574 |
| July 2025 | 18,238 |
| June 2025 | 17,592 |
| May 2025 | 15,826 |
| April 2025 | 13,997 |
| March 2025 | 15,455 |
| February 2025 | 9,806 |
| January 2025 | 9,452 |
| December 2024 | 7,953 |
| November 2024 | 9,082 |
| October 2024 | 14,387 |
| September 2024 | 14,155 |
| August 2024 | 18,366 |
| July 2024 | 17,279 |
| June 2024 | 16,264 |
| May 2024 | 11,856 |
| April 2024 | 12,362 |
| March 2024 | 13,311 |
| February 2024 | 10,455 |
| January 2024 | 7,102 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Ellis Solar LLC plant, and when do they retire?
1 operable generator totals 80 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 80 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| GER01 | Operating | Solar Photovoltaic | 80 | 2023 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Ellis Solar LLC plant?
EIA lists no joint owners for Ellis Solar LLC. 174 Power Global Corp. operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Ellis Solar LLC plant?
Ellis Solar LLC is in Midlothian, Ellis County, Texas, at 32.4672° N, 97.0543° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Texas are similar in size?
Texas has 225 operable solar plants with 30,739 MW of capacity, and Ellis Solar LLC's 80 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Swift Air Solar III | Ector | 100 | 21,342 |
| Tyson Nick | Lamar | 91 | 37,930 |
| G.S.E. One LLC | Fannin | 83 | 159,826 |
| Ellis Solar LLC | Ellis | 80 | 165,050 |
| Longbow Solar, LLC | Brazoria | 78 | 141,035 |
| Dileo Solar | Hill | 71 | 153,941 |
| Liberty Hybrid Solar and Storage Project | Harris | 67 | 53,440 |
Source: EIA Forms EIA-860 and EIA-923, 2025.