Solar power plant, Texas
Swift Air Solar III power plant, Texas
Swift Air Solar III is a 100 MW solar power plant in Ector County, Texas, operated by Origis Energy USA, Inc, and it generated 21,342 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 3rd percentile of U.S. solar plants. By 2025 generation it ranks 5,162nd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Swift Air Solar III plant run compared with other solar plants?
The Swift Air Solar III plant had a capacity factor of 2% in 2025 on 100 MW of net summer capacity, the 3rd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 9 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Swift Air Solar III | 2% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Swift Air Solar III plant generating more or less than last year?
Swift Air Solar III generated 21,342 MWh in 2025; EIA reports no 2024 total to compare.
| Period | MWh |
|---|---|
| 2024 | n/a |
| 2025 | 21,342 |
| 2026 through August | 184,642 |
Monthly generation, Nov 2025 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 30,195 |
| July 2026 | 28,852 |
| June 2026 | 23,980 |
| May 2026 | 23,868 |
| April 2026 | 19,549 |
| March 2026 | 24,942 |
| February 2026 | 17,181 |
| January 2026 | 16,075 |
| December 2025 | 15,630 |
| November 2025 | 5,712 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Swift Air Solar III plant, and when do they retire?
1 operable generator totals 100 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 100 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| OSAS3 | Operating | Solar Photovoltaic | 100 | 2025 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Swift Air Solar III plant?
EIA lists no joint owners for Swift Air Solar III. Origis Energy USA, Inc operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Swift Air Solar III plant?
Swift Air Solar III is in Odessa, Ector County, Texas, at 31.7231° N, 102.5196° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Texas are similar in size?
Texas has 225 operable solar plants with 30,739 MW of capacity, and Swift Air Solar III's 100 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| BPL Sol Solar LLC | Falls | 100 | 207,813 |
| Second Division Solar | Brazoria | 100 | 190,835 |
| Grizzly Ridge Solar | Hamilton | 100 | 117,694 |
| Swift Air Solar III | Ector | 100 | 21,342 |
| Tyson Nick | Lamar | 91 | 37,930 |
| G.S.E. One LLC | Fannin | 83 | 159,826 |
| Ellis Solar LLC | Ellis | 80 | 165,050 |
Source: EIA Forms EIA-860 and EIA-923, 2025.