Solar power plant, Alabama
Fort Benning Solar Facility, Alabama
Fort Benning Solar Facility is a 30 MW solar power plant in Russell County, Alabama, operated by Georgia Power Co, and it generated 56,032 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 35th percentile of U.S. solar plants. By 2025 generation it ranks 3,947th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Fort Benning Solar Facility plant run compared with other solar plants?
The Fort Benning Solar Facility plant had a capacity factor of 21% in 2025 on 30 MW of net summer capacity, the 35th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 78 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Fort Benning Solar Facility | 21% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Fort Benning Solar Facility plant generating more or less than last year?
Generation at Fort Benning Solar Facility rose 8.9% from 2024 to 2025, from 51,470 MWh to 56,032 MWh. Through August 2026 it is running 3.1% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 51,470 |
| 2025 | 56,032 |
| 2026 through August | 37,938 |
| 2025, same months | 39,155 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 4,629 |
| July 2026 | 5,667 |
| June 2026 | 4,910 |
| May 2026 | 5,075 |
| April 2026 | 4,839 |
| March 2026 | 5,366 |
| February 2026 | 4,016 |
| January 2026 | 3,436 |
| December 2025 | 3,002 |
| November 2025 | 4,449 |
| October 2025 | 4,653 |
| September 2025 | 4,773 |
| August 2025 | 4,617 |
| July 2025 | 5,573 |
| June 2025 | 5,231 |
| May 2025 | 5,241 |
| April 2025 | 5,240 |
| March 2025 | 5,409 |
| February 2025 | 4,009 |
| January 2025 | 3,835 |
| December 2024 | 3,619 |
| November 2024 | 3,183 |
| October 2024 | 5,105 |
| September 2024 | 3,497 |
| August 2024 | 5,268 |
| July 2024 | 4,414 |
| June 2024 | 5,267 |
| May 2024 | 4,781 |
| April 2024 | 4,477 |
| March 2024 | 4,085 |
| February 2024 | 4,053 |
| January 2024 | 3,721 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Fort Benning Solar Facility plant, and when do they retire?
1 operable generator totals 30 MW, with an average age of 10 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 30 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Solar Photovoltaic | 30 | 2015 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Fort Benning Solar Facility plant?
EIA lists no joint owners for Fort Benning Solar Facility. Georgia Power Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What does Georgia Power Co charge homes?
Georgia Power Co, the operator of Fort Benning Solar Facility, had an average residential price of 16.28¢ per kWh and an average bill of $161 a month in 2025 in Georgia.
| Measure | Price | Monthly bill | Against Alabama |
|---|---|---|---|
| Georgia Power Co | 16.28¢ | $161 | other state |
| Alabama average | 16.09¢ | $184 | |
| U.S. average | 17.23¢ | $151 | 7% higher |
Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.
Where is the Fort Benning Solar Facility plant?
Fort Benning Solar Facility is in Fort Mitchell, Russell County, Alabama, at 32.3040° N, 84.9899° W. It sits in the Southern Company Services, Inc. - Trans balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Alabama are similar in size?
Alabama has 12 operable solar plants with 746 MW of capacity, and Fort Benning Solar Facility's 30 MW is 4% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| TAI Huntsville Solar Hybrid | Madison | 32 | 62,449 |
| Fort Benning Solar Facility | Russell | 30 | 56,032 |
Source: EIA Forms EIA-860 and EIA-923, 2025.