Skip to main content
RateWatt

Wind power plant, Iowa

FPL Energy Crystal Lake Wind II LLC power plant, Iowa

FPL Energy Crystal Lake Wind II LLC is a 200 MW wind power plant in Hancock County, Iowa, operated by FPL Energy Crystal Lake Wind II LLC, and it generated 721,542 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.0% of the generation reported in Iowa, and its capacity factor sits at the 79th percentile of U.S. wind plants. By 2025 generation it ranks 966th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

200 MWNameplate capacity
41%Capacity factor, 2025, 79th percentile, on 199 MW net summer
1.0%Of IA generation, 2025
16 yearsAverage generator age, by MW

How hard does the FPL Energy Crystal Lake Wind II LLC plant run compared with other wind plants?

The FPL Energy Crystal Lake Wind II LLC plant had a capacity factor of 41% in 2025 on 199 MW of net summer capacity, the 79th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 151 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
FPL Energy Crystal Lake Wind II LLC41%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the FPL Energy Crystal Lake Wind II LLC plant generating more or less than last year?

Generation at FPL Energy Crystal Lake Wind II LLC fell 2.1% from 2024 to 2025, from 737,341 MWh to 721,542 MWh. Through August 2026 it is running 4.3% behind the same months of 2025.

Net generation by period
PeriodMWh
2024737,341
2025721,542
2026 through August442,599
2025, same months462,514
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202630,428
July 202624,622
June 202650,242
May 202656,950
April 202672,607
March 202679,369
February 202664,024
January 202664,357
December 202577,057
November 202567,232
October 202576,107
September 202538,632
August 202532,219
July 202530,727
June 202546,555
May 202548,212
April 202579,881
March 202582,762
February 202565,237
January 202576,921
December 202461,368
November 202470,946
October 202479,279
September 202450,596
August 202437,547
July 202432,426
June 202453,053
May 202459,739
April 202486,149
March 202485,585
February 202467,676
January 202452,977

Source: EIA Form EIA-923, through August 2026.

How much of Iowa's electricity comes from the FPL Energy Crystal Lake Wind II LLC plant?

FPL Energy Crystal Lake Wind II LLC made 1.0% of the 74,502,373 MWh reported by Iowa plants in 2025, from 0.8% of the state's 24,817 MW of capacity. Its share of output is 1.2 times its share of capacity. By capacity it is the 38th largest of 306 plants in Iowa, the 1,524th largest of 14,327 in the U.S. and the 277th largest of 1,358 wind plants. By 2025 generation it is the 34th largest of 283 generating plants in the state.

FPL Energy Crystal Lake Wind II LLC within Iowa, 2025
MeasureThis plantIowaShare
Capacity (MW)20024,8170.8%
Generation (MWh)721,54274,502,3731.0%
Wind capacity (MW)20013,4101.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the FPL Energy Crystal Lake Wind II LLC plant, and when do they retire?

1 operable generator totals 200 MW, with an average age of 16 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s1200100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
CL25OperatingOnshore Wind Turbine2002009n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the FPL Energy Crystal Lake Wind II LLC plant?

EIA lists no joint owners for FPL Energy Crystal Lake Wind II LLC. FPL Energy Crystal Lake Wind II LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the FPL Energy Crystal Lake Wind II LLC plant?

FPL Energy Crystal Lake Wind II LLC is in Britt, Hancock County, Iowa, at 43.2737° N, 93.8000° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Iowa are similar in size?

Iowa has 123 operable wind plants with 13,410 MW of capacity, and FPL Energy Crystal Lake Wind II LLC's 200 MW is 1% of that.

Wind plants in Iowa around this size
PlantCountyMW2025 MWh
Whispering Willow NorthFranklin201733,862
CenturyHamilton201608,889
Ida Grove IIIda201726,554
FPL Energy Crystal Lake Wind II LLCHancock200721,542
Heartland Divide IIAudubon200798,264
Golden PlainsWinnebago200736,798
Whispering Willow Wind Farm - EastFranklin200404,628

Source: EIA Forms EIA-860 and EIA-923, 2025.