Skip to main content
RateWatt

Wind power plant, Iowa

Whispering Willow North wind power plant, Iowa

Whispering Willow North is a 201 MW wind power plant in Franklin County, Iowa, operated by Interstate Power and Light Co, and it generated 733,862 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.0% of the generation reported in Iowa, and its capacity factor sits at the 80th percentile of U.S. wind plants. By 2025 generation it ranks 950th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

201 MWNameplate capacity
42%Capacity factor, 2025, 80th percentile, on 201 MW net summer
1.0%Of IA generation, 2025
5 yearsAverage generator age, by MW

How hard does the Whispering Willow North plant run compared with other wind plants?

The Whispering Willow North plant had a capacity factor of 42% in 2025 on 201 MW of net summer capacity, the 80th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 152 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Whispering Willow North42%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Whispering Willow North plant generating more or less than last year?

Generation at Whispering Willow North fell 7.7% from 2024 to 2025, from 795,509 MWh to 733,862 MWh. Through August 2026 it is running 1.1% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024795,509
2025733,862
2026 through August489,788
2025, same months484,527
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202636,491
July 202629,322
June 202655,202
May 202664,687
April 202680,172
March 202681,299
February 202668,652
January 202673,963
December 202578,054
November 202573,963
October 202578,723
September 202518,595
August 202512,753
July 202535,380
June 202552,889
May 202552,727
April 202578,998
March 202587,022
February 202577,656
January 202587,102
December 202467,831
November 202472,759
October 202484,936
September 202454,306
August 202442,921
July 202436,841
June 202461,839
May 202463,802
April 202485,983
March 202487,274
February 202475,762
January 202461,255

Source: EIA Form EIA-923, through August 2026.

How much of Iowa's electricity comes from the Whispering Willow North plant?

Whispering Willow North made 1.0% of the 74,502,373 MWh reported by Iowa plants in 2025, from 0.8% of the state's 24,817 MW of capacity. Its share of output is 1.2 times its share of capacity. By capacity it is the 35th largest of 306 plants in Iowa, the 1,497th largest of 14,327 in the U.S. and the 250th largest of 1,358 wind plants. By 2025 generation it is the 32nd largest of 283 generating plants in the state.

Whispering Willow North within Iowa, 2025
MeasureThis plantIowaShare
Capacity (MW)20124,8170.8%
Generation (MWh)733,86274,502,3731.0%
Wind capacity (MW)20113,4101.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Whispering Willow North plant, and when do they retire?

1 operable generator totals 201 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1201100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingOnshore Wind Turbine2012020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Whispering Willow North plant?

EIA lists no joint owners for Whispering Willow North. Interstate Power and Light Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Interstate Power and Light Co charge homes?

Interstate Power and Light Co, the operator of Whispering Willow North, had an average residential price of 17.77¢ per kWh and an average bill of $131 a month in 2025, 30% above the Iowa average of 13.62¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Iowa
Interstate Power and Light Co17.77¢$13130% higher
Iowa average13.62¢$117
U.S. average17.23¢$15126% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Whispering Willow North plant?

Whispering Willow North is in Latimer, Franklin County, Iowa, at 42.7750° N, 93.4181° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Iowa are similar in size?

Iowa has 123 operable wind plants with 13,410 MW of capacity, and Whispering Willow North's 201 MW is 2% of that.

Wind plants in Iowa around this size
PlantCountyMW2025 MWh
Ledyard Windpower, LLCKossuth207595,925
Plymouth WindPlymouth203799,637
Chickasaw Wind FarmChickasaw202645,362
Whispering Willow NorthFranklin201733,862
CenturyHamilton201608,889
Ida Grove IIIda201726,554
FPL Energy Crystal Lake Wind II LLCHancock200721,542

Source: EIA Forms EIA-860 and EIA-923, 2025.