Skip to main content
RateWatt

Solar power plant, Colorado

Garnet Mesa Solar power plant, Colorado

Garnet Mesa Solar is a 80 MW solar power plant in Delta County, Colorado, operated by Garnet Mesa Solar LLC, and it generated 75,003 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Colorado, and its capacity factor sits at the 7th percentile of U.S. solar plants. By 2025 generation it ranks 3,705th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

80 MWNameplate capacity
11%Capacity factor, 2025, 7th percentile, on 80 MW net summer
0.1%Of CO generation, 2025
Under 1 yearAverage generator age, by MW

How hard does the Garnet Mesa Solar plant run compared with other solar plants?

The Garnet Mesa Solar plant had a capacity factor of 11% in 2025 on 80 MW of net summer capacity, the 7th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 39 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Garnet Mesa Solar11%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Garnet Mesa Solar plant generating more or less than last year?

Garnet Mesa Solar generated 75,003 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 601.3% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024n/a
202575,003
2026 through August154,107
2025, same months21,975
Monthly generation, Aug 2025 to Aug 2026
MonthMWh
August 202621,577
July 202623,455
June 202624,552
May 202623,532
April 202618,369
March 202619,593
February 202612,262
January 202610,767
December 20258,552
November 202510,169
October 202516,053
September 202518,254
August 202521,975

Source: EIA Form EIA-923, through August 2026.

How much of Colorado's electricity comes from the Garnet Mesa Solar plant?

Garnet Mesa Solar made 0.1% of the 55,830,894 MWh reported by Colorado plants in 2025, from 0.4% of the state's 22,712 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 66th largest of 321 plants in Colorado, the 2,965th largest of 14,327 in the U.S. and the 564th largest of 7,223 solar plants. By 2025 generation it is the 74th largest of 292 generating plants in the state.

Garnet Mesa Solar within Colorado, 2025
MeasureThis plantColoradoShare
Capacity (MW)8022,7120.4%
Generation (MWh)75,00355,830,8940.1%
Solar capacity (MW)803,2632.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Garnet Mesa Solar plant, and when do they retire?

1 operable generator totals 80 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s180100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GMSOperatingSolar Photovoltaic802025n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Garnet Mesa Solar plant?

EIA lists no joint owners for Garnet Mesa Solar. Garnet Mesa Solar LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Garnet Mesa Solar plant?

Garnet Mesa Solar is in Delta, Delta County, Colorado, at 38.7406° N, 107.9825° W. It sits in the Western Area Power Administration - Rocky Mountain Region balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Colorado are similar in size?

Colorado has 181 operable solar plants with 3,263 MW of capacity, and Garnet Mesa Solar's 80 MW is 2% of that.

Solar plants in Colorado around this size
PlantCountyMW2025 MWh
Comanche SolarPueblo120227,746
Dolores Canyon SolarDolores11021,452
Pioneer Solar (CO), LLCAdams80179,753
Garnet Mesa SolarDelta8075,003
Hunter Solar, LLC (CO)Arapahoe75198,138
Palmer SolarEl Paso60140,246
Hooper SolarAlamosa52121,919

Source: EIA Forms EIA-860 and EIA-923, 2025.