Glass Sands Wind Facility, Oklahoma

Glass Sands Wind Facility is a 117 MW wind power plant in Murray County, Oklahoma, operated by Southern Power Co, and it generated 420,520 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.5% of the generation reported in Oklahoma, and its capacity factor sits at the 75th percentile of U.S. wind plants. By 2025 generation it ranks 1,531st of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

117 MWNameplate capacity
41%Capacity factor, 2025, 75th percentile, on 118 MW net summer
0.5%Of OK generation, 2025
4 yearsAverage generator age, by MW

How hard does the Glass Sands Wind Facility plant run compared with other wind plants?

The Glass Sands Wind Facility plant had a capacity factor of 41% in 2025 on 118 MW of net summer capacity, the 75th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 148 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Glass Sands Wind Facility41%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Glass Sands Wind Facility plant generating more or less than last year?

Generation at Glass Sands Wind Facility fell 3.4% from 2024 to 2025, from 435,201 MWh to 420,520 MWh. Through August 2026 it is running 18.8% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024435,201
2025420,520
2026 through August325,609
2025, same months274,118
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202639,837
July 202632,137
June 202639,987
May 202635,513
April 202644,818
March 202650,356
February 202641,963
January 202640,998
December 202546,640
November 202543,039
October 202534,195
September 202522,528
August 202525,921
July 202530,395
June 202532,715
May 202531,662
April 202533,850
March 202547,926
February 202534,058
January 202537,591
December 202438,295
November 202440,136
October 202443,263
September 202423,121
August 202432,023
July 202429,010
June 202435,445
May 202417,369
April 202447,067
March 202446,585
February 202447,146
January 202435,741

Source: EIA Form EIA-923, through August 2026.

How much of Oklahoma's electricity comes from the Glass Sands Wind Facility plant?

Glass Sands Wind Facility made 0.5% of the 89,758,877 MWh reported by Oklahoma plants in 2025, from 0.3% of the state's 35,828 MW of capacity. Its share of output is 1.4 times its share of capacity. By capacity it is the 79th largest of 143 plants in Oklahoma, the 2,368th largest of 14,327 in the U.S. and the 574th largest of 1,358 wind plants. By 2025 generation it is the 62nd largest of 135 generating plants in the state.

Glass Sands Wind Facility within Oklahoma, 2025
MeasureThis plantOklahomaShare
Capacity (MW)11735,8280.3%
Generation (MWh)420,52089,758,8770.5%
Wind capacity (MW)11713,3440.9%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Glass Sands Wind Facility plant, and when do they retire?

1 operable generator totals 117 MW, with an average age of 4 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1117100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingOnshore Wind Turbine1172021n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Glass Sands Wind Facility plant?

Glass Sands Wind Energy, LLC is the only joint owner reported for Glass Sands Wind Facility, with 100.0%. Southern Power Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Glass Sands Wind Facility plant?

Glass Sands Wind Facility is in Sulphur, Murray County, Oklahoma, at 34.5142° N, 96.9159° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Oklahoma are similar in size?

Oklahoma has 69 operable wind plants with 13,344 MW of capacity, and Glass Sands Wind Facility's 117 MW is 1% of that.

Wind plants in Oklahoma around this size
PlantCountyMW2025 MWh
Minco Wind IV, LLCCanadian130516,942
Red Hills Wind Project LLCRoger Mills123190,222
Centennial Wind FarmHarper120156,716
Glass Sands Wind FacilityMurray117420,520
Drift Sand Wind Project LLCGrady108344,106
Oklahoma Wind Energy CenterWoodward102140,563
OU Spirit Wind FarmWoodward101127,120