Skip to main content
RateWatt

Wind power plant, Oklahoma

Minco Wind IV, LLC power plant, Oklahoma

Minco Wind IV, LLC is a 130 MW wind power plant in Canadian County, Oklahoma, operated by Minco Wind IV, LLC, and it generated 516,942 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.6% of the generation reported in Oklahoma, and its capacity factor sits at the 92nd percentile of U.S. wind plants. By 2025 generation it ranks 1,308th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

130 MWNameplate capacity
45%Capacity factor, 2025, 92nd percentile, on 130 MW net summer
0.6%Of OK generation, 2025
7 yearsAverage generator age, by MW

How hard does the Minco Wind IV, LLC plant run compared with other wind plants?

The Minco Wind IV, LLC plant had a capacity factor of 45% in 2025 on 130 MW of net summer capacity, the 92nd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 166 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Minco Wind IV, LLC45%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Minco Wind IV, LLC plant generating more or less than last year?

Generation at Minco Wind IV, LLC rose 33.1% from 2024 to 2025, from 388,330 MWh to 516,942 MWh. Through August 2026 it is running 21.4% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024388,330
2025516,942
2026 through August402,134
2025, same months331,212
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202646,365
July 202638,933
June 202649,221
May 202646,975
April 202661,685
March 202660,002
February 202646,228
January 202652,725
December 202555,907
November 202547,390
October 202548,648
September 202533,785
August 202536,104
July 202541,355
June 202541,132
May 202530,569
April 202548,359
March 202553,011
February 202541,597
January 202539,085
December 202430,908
November 202426,788
October 202430,205
September 202425,978
August 202439,880
July 202437,433
June 202440,006
May 202438,135
April 202424,385
March 202432,030
February 202434,872
January 202427,710

Source: EIA Form EIA-923, through August 2026.

How much of Oklahoma's electricity comes from the Minco Wind IV, LLC plant?

Minco Wind IV, LLC made 0.6% of the 89,758,877 MWh reported by Oklahoma plants in 2025, from 0.4% of the state's 35,828 MW of capacity. Its share of output is 1.6 times its share of capacity. By capacity it is the 72nd largest of 143 plants in Oklahoma, the 2,218th largest of 14,327 in the U.S. and the 538th largest of 1,358 wind plants. By 2025 generation it is the 46th largest of 135 generating plants in the state.

Minco Wind IV, LLC within Oklahoma, 2025
MeasureThis plantOklahomaShare
Capacity (MW)13035,8280.4%
Generation (MWh)516,94289,758,8770.6%
Wind capacity (MW)13013,3441.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Minco Wind IV, LLC plant, and when do they retire?

1 operable generator totals 130 MW, with an average age of 7 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s1130100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
MIVOperatingOnshore Wind Turbine1302018n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Minco Wind IV, LLC plant?

EIA lists no joint owners for Minco Wind IV, LLC. Minco Wind IV, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Minco Wind IV, LLC plant?

Minco Wind IV, LLC is in Hinton, Canadian County, Oklahoma, at 35.3810° N, 98.2696° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Oklahoma are similar in size?

Oklahoma has 69 operable wind plants with 13,344 MW of capacity, and Minco Wind IV, LLC's 130 MW is 1% of that.

Wind plants in Oklahoma around this size
PlantCountyMW2025 MWh
Rockhaven Wind Project, LLCMurray140470,107
Dempsey Ridge Wind FarmRoger Mills132118,282
Taloga Wind LLCDewey130188,185
Minco Wind IV, LLCCanadian130516,942
Red Hills Wind Project LLCRoger Mills123190,222
Centennial Wind FarmHarper120156,716
Glass Sands Wind FacilityMurray117420,520

Source: EIA Forms EIA-860 and EIA-923, 2025.