Wind power plant, Oklahoma
Red Hills Wind Project LLC power plant, Oklahoma
Red Hills Wind Project LLC is a 123 MW wind power plant in Roger Mills County, Oklahoma, operated by Acciona Wind Energy USA LLC, and it generated 190,222 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Oklahoma, and its capacity factor sits at the 7th percentile of U.S. wind plants. By 2025 generation it ranks 2,560th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Red Hills Wind Project LLC plant run compared with other wind plants?
The Red Hills Wind Project LLC plant had a capacity factor of 18% in 2025 on 123 MW of net summer capacity, the 7th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 64 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Red Hills Wind Project LLC | 18% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Red Hills Wind Project LLC plant generating more or less than last year?
Generation at Red Hills Wind Project LLC rose 57.1% from 2024 to 2025, from 121,067 MWh to 190,222 MWh.
| Period | MWh |
|---|---|
| 2024 | 121,067 |
| 2025 | 190,222 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 19,842 |
| November 2025 | 14,357 |
| October 2025 | 15,845 |
| September 2025 | 14,576 |
| August 2025 | 18,362 |
| July 2025 | 23,619 |
| June 2025 | 19,217 |
| May 2025 | 14,515 |
| April 2025 | 11,447 |
| March 2025 | 11,481 |
| February 2025 | 13,969 |
| January 2025 | 12,992 |
| December 2024 | 6,583 |
| November 2024 | 6,989 |
| October 2024 | 15,325 |
| September 2024 | 12,419 |
| August 2024 | 18,712 |
| July 2024 | 14,773 |
| June 2024 | 12,938 |
| May 2024 | 6,432 |
| April 2024 | 5,935 |
| March 2024 | 4,675 |
| February 2024 | 8,294 |
| January 2024 | 7,992 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Red Hills Wind Project LLC plant, and when do they retire?
1 operable generator totals 123 MW, with an average age of 17 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 1 | 123 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| RH | Operating | Onshore Wind Turbine | 123 | 2008 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Red Hills Wind Project LLC plant?
EIA lists no joint owners for Red Hills Wind Project LLC. Acciona Wind Energy USA LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Red Hills Wind Project LLC plant?
Red Hills Wind Project LLC is in Hammon, Roger Mills County, Oklahoma, at 35.5350° N, 99.3828° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Oklahoma are similar in size?
Oklahoma has 69 operable wind plants with 13,344 MW of capacity, and Red Hills Wind Project LLC's 123 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Dempsey Ridge Wind Farm | Roger Mills | 132 | 118,282 |
| Taloga Wind LLC | Dewey | 130 | 188,185 |
| Minco Wind IV, LLC | Canadian | 130 | 516,942 |
| Red Hills Wind Project LLC | Roger Mills | 123 | 190,222 |
| Centennial Wind Farm | Harper | 120 | 156,716 |
| Glass Sands Wind Facility | Murray | 117 | 420,520 |
| Drift Sand Wind Project LLC | Grady | 108 | 344,106 |
Source: EIA Forms EIA-860 and EIA-923, 2025.