Hydro power plant, Tennessee

J P Priest hydroelectric power plant, Tennessee

J P Priest is a 28 MW hydro power plant in Davidson County, Tennessee, operated by USCE-Nashville District, and it generated 60,375 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Tennessee, and its capacity factor sits at the 27th percentile of U.S. hydro plants. By 2025 generation it ranks 3,870th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

28 MWNameplate capacity
23%Capacity factor, 2025, 27th percentile, on 30 MW net summer
0.1%Of TN generation, 2025
55 yearsAverage generator age, by MW

How hard does the J P Priest plant run compared with other hydro plants?

The J P Priest plant had a capacity factor of 23% in 2025 on 30 MW of net summer capacity, the 27th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 84 days at full output out of 365.

0%Shaded: the middle half of hydro plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
J P Priest23%
Hydro plants, 75th percentile44%
Hydro plants, median33%
Hydro plants, 25th percentile22%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the J P Priest plant generating more or less than last year?

J P Priest generated 60,375 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 8 months, so the two years are not compared.

Net generation by period
PeriodMWh
202453,562
202560,375
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 20255,820
November 20255,880
October 20250
September 20250
August 20250
July 20250
June 20251,050
May 20257,545
April 20258,640
March 202511,040
February 202513,710
January 20256,690
December 202410,206
November 20242,700
October 2024840
September 20240
August 20240
July 20240
June 20240
May 20247,386
April 20241,665
March 20248,100
February 202414,685
January 20247,980

Source: EIA Form EIA-923, through August 2026.

How much of Tennessee's electricity comes from the J P Priest plant?

J P Priest made 0.1% of the 74,359,316 MWh reported by Tennessee plants in 2025, from 0.1% of the state's 23,342 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 47th largest of 99 plants in Tennessee, the 4,456th largest of 14,327 in the U.S. and the 379th largest of 1,393 hydro plants. By 2025 generation it is the 48th largest of 95 generating plants in the state.

J P Priest within Tennessee, 2025
MeasureThis plantTennesseeShare
Capacity (MW)2823,3420.1%
Generation (MWh)60,37574,359,3160.1%
Hydro capacity (MW)282,5201.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the J P Priest plant, and when do they retire?

1 operable generator totals 28 MW, with an average age of 55 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
1970s128100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingConventional Hydroelectric281970n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the J P Priest plant?

EIA lists no joint owners for J P Priest. USCE-Nashville District operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the J P Priest plant?

J P Priest is in Nashville, Davidson County, Tennessee, at 36.1564° N, 86.6186° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which hydro plants in Tennessee are similar in size?

Tennessee has 28 operable hydro plants with 2,520 MW of capacity, and J P Priest's 28 MW is 1% of that.

Hydro plants in Tennessee around this size
PlantCountyMW2025 MWh
CheathamDickson36191,448
Great Falls (TN)Warren34131,052
Ocoee 3Polk29141,310
J P PriestDavidson2860,375
Ocoee 2Polk2398,148
Ocoee 1Polk1965,629

Source: EIA Forms EIA-860 and EIA-923, 2025.