Hydro power plant, Tennessee
Ocoee 2 hydroelectric power plant, Tennessee
Ocoee 2 is a 23 MW hydro power plant in Polk County, Tennessee, operated by Tennessee Valley Authority, and it generated 98,148 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Tennessee, and its capacity factor sits at the 83rd percentile of U.S. hydro plants. By 2025 generation it ranks 3,414th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Ocoee 2 plant run compared with other hydro plants?
The Ocoee 2 plant had a capacity factor of 48% in 2025 on 23.4 MW of net summer capacity, the 83rd percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 175 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Ocoee 2 | 48% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Ocoee 2 plant generating more or less than last year?
Generation at Ocoee 2 rose 13.3% from 2024 to 2025, from 86,652 MWh to 98,148 MWh.
| Period | MWh |
|---|---|
| 2024 | 86,652 |
| 2025 | 98,148 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 6,714 |
| November 2025 | 7,446 |
| October 2025 | 5,761 |
| September 2025 | 6,302 |
| August 2025 | 7,955 |
| July 2025 | 4,748 |
| June 2025 | 7,978 |
| May 2025 | 11,513 |
| April 2025 | 10,726 |
| March 2025 | 8,064 |
| February 2025 | 9,771 |
| January 2025 | 11,170 |
| December 2024 | 9,435 |
| November 2024 | 6,110 |
| October 2024 | 6,805 |
| September 2024 | 5,254 |
| August 2024 | 4,299 |
| July 2024 | 5,310 |
| June 2024 | 2,853 |
| May 2024 | 2,355 |
| April 2024 | 9,402 |
| March 2024 | 11,564 |
| February 2024 | 12,131 |
| January 2024 | 11,134 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Ocoee 2 plant, and when do they retire?
2 operable generators total 23 MW, with an average age of 112 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1910s | 2 | 23 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 12 | 1913 | n/a |
| 2 | Operating | Conventional Hydroelectric | 12 | 1913 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Ocoee 2 plant?
EIA lists no joint owners for Ocoee 2. Tennessee Valley Authority operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Ocoee 2 plant?
Ocoee 2 is in Benton, Polk County, Tennessee, at 35.0823° N, 84.4912° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Tennessee are similar in size?
Tennessee has 28 operable hydro plants with 2,520 MW of capacity, and Ocoee 2's 23 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Great Falls (TN) | Warren | 34 | 131,052 |
| Ocoee 3 | Polk | 29 | 141,310 |
| J P Priest | Davidson | 28 | 60,375 |
| Ocoee 2 | Polk | 23 | 98,148 |
| Ocoee 1 | Polk | 19 | 65,629 |
Source: EIA Forms EIA-860 and EIA-923, 2025.