Hydro power plant, Tennessee
Ocoee 3 hydroelectric power plant, Tennessee
Ocoee 3 is a 28.8 MW hydro power plant in Polk County, Tennessee, operated by Tennessee Valley Authority, and it generated 141,310 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Tennessee, and its capacity factor sits at the 93rd percentile of U.S. hydro plants. By 2025 generation it ranks 2,997th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Ocoee 3 plant run compared with other hydro plants?
The Ocoee 3 plant had a capacity factor of 56% in 2025 on 28.6 MW of net summer capacity, the 93rd percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 206 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Ocoee 3 | 56% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Ocoee 3 plant generating more or less than last year?
Generation at Ocoee 3 fell 6.9% from 2024 to 2025, from 151,739 MWh to 141,310 MWh.
| Period | MWh |
|---|---|
| 2024 | 151,739 |
| 2025 | 141,310 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 8,889 |
| November 2025 | 9,925 |
| October 2025 | 6,831 |
| September 2025 | 10,553 |
| August 2025 | 14,069 |
| July 2025 | 10,182 |
| June 2025 | 14,318 |
| May 2025 | 18,702 |
| April 2025 | 16,832 |
| March 2025 | 10,609 |
| February 2025 | 5,003 |
| January 2025 | 15,397 |
| December 2024 | 13,096 |
| November 2024 | 7,590 |
| October 2024 | 10,923 |
| September 2024 | 10,110 |
| August 2024 | 8,791 |
| July 2024 | 10,594 |
| June 2024 | 11,655 |
| May 2024 | 16,100 |
| April 2024 | 13,995 |
| March 2024 | 16,348 |
| February 2024 | 15,494 |
| January 2024 | 17,043 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Ocoee 3 plant, and when do they retire?
1 operable generator totals 28.8 MW, with an average age of 82 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1940s | 1 | 29 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 29 | 1943 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Ocoee 3 plant?
EIA lists no joint owners for Ocoee 3. Tennessee Valley Authority operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Ocoee 3 plant?
Ocoee 3 is in Benton, Polk County, Tennessee, at 35.0750° N, 84.4833° W. It sits in the Tennessee Valley Authority balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Tennessee are similar in size?
Tennessee has 28 operable hydro plants with 2,520 MW of capacity, and Ocoee 3's 28.8 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| South Holston | Sullivan | 39 | 121,520 |
| Cheatham | Dickson | 36 | 191,448 |
| Great Falls (TN) | Warren | 34 | 131,052 |
| Ocoee 3 | Polk | 29 | 141,310 |
| J P Priest | Davidson | 28 | 60,375 |
| Ocoee 2 | Polk | 23 | 98,148 |
| Ocoee 1 | Polk | 19 | 65,629 |
Source: EIA Forms EIA-860 and EIA-923, 2025.