Hydro power plant, Florida
J Woodruff hydroelectric power plant, Florida
J Woodruff is a 43.5 MW hydro power plant in Gadsden County, Florida, operated by USCE-Mobile District, and it generated 228,459 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Florida, and its capacity factor sits at the 96th percentile of U.S. hydro plants. By 2025 generation it ranks 2,324th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the J Woodruff plant run compared with other hydro plants?
The J Woodruff plant had a capacity factor of 60% in 2025 on 43.5 MW of net summer capacity, the 96th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 219 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| J Woodruff | 60% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the J Woodruff plant generating more or less than last year?
Generation at J Woodruff rose 28.9% from 2024 to 2025, from 177,238 MWh to 228,459 MWh.
| Period | MWh |
|---|---|
| 2024 | 177,238 |
| 2025 | 228,459 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 10,238 |
| November 2025 | 12,180 |
| October 2025 | 12,078 |
| September 2025 | 14,251 |
| August 2025 | 26,152 |
| July 2025 | 20,728 |
| June 2025 | 24,577 |
| May 2025 | 25,062 |
| April 2025 | 22,175 |
| March 2025 | 23,811 |
| February 2025 | 13,674 |
| January 2025 | 23,533 |
| December 2024 | 20,172 |
| November 2024 | 19,287 |
| October 2024 | 15,166 |
| September 2024 | 13,846 |
| August 2024 | 16,209 |
| July 2024 | 17,095 |
| June 2024 | 15,420 |
| May 2024 | 10,686 |
| April 2024 | 14,055 |
| March 2024 | 7,703 |
| February 2024 | 10,427 |
| January 2024 | 17,172 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the J Woodruff plant, and when do they retire?
3 operable generators total 43.5 MW, with an average age of 23 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860. 3 have already retired, totalling 30 MW.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2000s | 3 | 44 | 100% | none reported |
Every generator, 6 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 3A | Operating | Conventional Hydroelectric | 15 | 2001 | n/a |
| 2A | Operating | Conventional Hydroelectric | 15 | 2002 | n/a |
| 1A | Operating | Conventional Hydroelectric | 15 | 2003 | n/a |
| 1 | Retired | Conventional Hydroelectric | 10 | 1957 | 2003 |
| 2 | Retired | Conventional Hydroelectric | 10 | 1957 | 2002 |
| 3 | Retired | Conventional Hydroelectric | 10 | 1957 | 2001 |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the J Woodruff plant?
EIA lists no joint owners for J Woodruff. USCE-Mobile District operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the J Woodruff plant?
J Woodruff is in Chattahoochee, Gadsden County, Florida, at 30.7086° N, 84.8639° W. It sits in the Florida Power & Light Company balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which Florida power plants are similar in size?
J Woodruff is the only operable hydro plant in Florida, so these are the plants of any fuel closest to its 43.5 MW.
| Plant | Fuel | County | MW | 2025 MWh |
|---|---|---|---|---|
| Hillsborough County Resource Recovery | Biomass | Hillsborough | 47 | 201,072 |
| Tropicana Products Bradenton | Natural gas | Manatee | 47 | 195,364 |
| Big Bend II Solar | Solar | Hillsborough | 46 | 86,395 |
| J Woodruff | Hydro | Gadsden | 44 | 228,459 |
| Fernandina Plant | Biomass | Nassau | 42 | 177,710 |
| FL Solar 4, LLC | Solar | Leon | 42 | 69,918 |
| Gulf Coast Solar Center II | Solar | Santa Rosa | 40 | 78,781 |
Source: EIA Forms EIA-860 and EIA-923, 2025.