Kelly Creek Wind Project is a 184 MW wind power plant in Ford County, Illinois, operated by EDF Renewable Asset Holdings, Inc., and it generated 621,703 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Illinois, and its capacity factor sits at the 68th percentile of U.S. wind plants. By 2025 generation it ranks 1,101st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Kelly Creek Wind Project plant run compared with other wind plants?
The Kelly Creek Wind Project plant had a capacity factor of 39% in 2025 on 184 MW of net summer capacity, the 68th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 141 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Kelly Creek Wind Project | 39% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Kelly Creek Wind Project plant generating more or less than last year?
Generation at Kelly Creek Wind Project fell 4.5% from 2024 to 2025, from 650,922 MWh to 621,703 MWh. Through August 2026 it is running 1.8% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 650,922 |
| 2025 | 621,703 |
| 2026 through August | 427,029 |
| 2025, same months | 419,660 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 25,900 |
| July 2026 | 22,368 |
| June 2026 | 44,616 |
| May 2026 | 49,871 |
| April 2026 | 76,200 |
| March 2026 | 80,059 |
| February 2026 | 58,724 |
| January 2026 | 69,291 |
| December 2025 | 68,426 |
| November 2025 | 52,164 |
| October 2025 | 57,884 |
| September 2025 | 23,569 |
| August 2025 | 24,116 |
| July 2025 | 22,479 |
| June 2025 | 37,826 |
| May 2025 | 54,098 |
| April 2025 | 65,213 |
| March 2025 | 84,066 |
| February 2025 | 61,394 |
| January 2025 | 70,468 |
| December 2024 | 68,651 |
| November 2024 | 67,188 |
| October 2024 | 59,269 |
| September 2024 | 28,767 |
| August 2024 | 25,667 |
| July 2024 | 21,547 |
| June 2024 | 51,770 |
| May 2024 | 51,016 |
| April 2024 | 76,759 |
| March 2024 | 79,923 |
| February 2024 | 58,452 |
| January 2024 | 61,913 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Kelly Creek Wind Project plant, and when do they retire?
1 operable generator totals 184 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 184 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| WND1 | Operating | Onshore Wind Turbine | 184 | 2016 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Kelly Creek Wind Project plant?
EIA lists no joint owners for Kelly Creek Wind Project. EDF Renewable Asset Holdings, Inc. operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Kelly Creek Wind Project plant?
Kelly Creek Wind Project is in Cabery, Ford County, Illinois, at 40.9675° N, 88.1975° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Illinois are similar in size?
Illinois has 55 operable wind plants with 8,458 MW of capacity, and Kelly Creek Wind Project's 184 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Green River Wind Farm | Lee | 194 | 497,093 |
| Hilltopper Wind Project | Logan | 185 | 473,987 |
| Glacier Sands Wind Power, LLC | Mason | 185 | 632,305 |
| Kelly Creek Wind Project | Ford | 184 | 621,703 |
| Pilot Hill Wind Farm | Kankakee | 175 | 588,568 |
| Moraine Sands Wind Power | Mason | 171 | 574,203 |
| Settlers Trail Wind Farm LLC | Iroquois | 150 | 320,385 |
Source: EIA Forms EIA-860 and EIA-923, 2025.