Skip to main content
RateWatt

Solar power plant, Texas

Lamesa II solar power plant, Texas

Lamesa II is a 50 MW solar power plant in Dawson County, Texas, operated by Lamesa Solar II, L.L.C., and it generated 120,697 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 80th percentile of U.S. solar plants. By 2025 generation it ranks 3,189th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

50 MWNameplate capacity
28%Capacity factor, 2025, 80th percentile, on 50 MW net summer
3,189thU.S. rank by generation, 2025
7 yearsAverage generator age, by MW

How hard does the Lamesa II plant run compared with other solar plants?

The Lamesa II plant had a capacity factor of 28% in 2025 on 50 MW of net summer capacity, the 80th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 101 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Lamesa II28%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Lamesa II plant generating more or less than last year?

Generation at Lamesa II fell 1.1% from 2024 to 2025, from 121,991 MWh to 120,697 MWh. Through August 2026 it is running 5.6% behind the same months of 2025.

Net generation by period
PeriodMWh
2024121,991
2025120,697
2026 through August80,653
2025, same months85,418
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202614,850
July 202614,256
June 202610,409
May 202611,216
April 20268,746
March 20267,919
February 20267,589
January 20265,668
December 20256,752
November 20258,062
October 20259,838
September 202510,627
August 202511,604
July 202511,804
June 202512,445
May 202512,462
April 20259,421
March 202510,815
February 20258,557
January 20258,310
December 20247,217
November 20246,647
October 20248,855
September 202410,667
August 202413,652
July 202414,046
June 202413,043
May 202413,113
April 20249,943
March 20249,702
February 20248,288
January 20246,818

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Lamesa II plant?

Lamesa II made 0.0% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.0% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 594th largest of 1,023 plants in Texas, the 3,754th largest of 14,327 in the U.S. and the 882nd largest of 7,223 solar plants. By 2025 generation it is the 484th largest of 816 generating plants in the state.

Lamesa II within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)50195,9660.0%
Generation (MWh)120,697592,896,1760.0%
Solar capacity (MW)5030,7390.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Lamesa II plant, and when do they retire?

1 operable generator totals 50 MW, with an average age of 7 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s150100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
IVORYOperatingSolar Photovoltaic502018n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Lamesa II plant?

EIA lists no joint owners for Lamesa II. Lamesa Solar II, L.L.C. operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Lamesa II plant?

Lamesa II is in Lamesa, Dawson County, Texas, at 32.7133° N, 101.8852° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Texas are similar in size?

Texas has 225 operable solar plants with 30,739 MW of capacity, and Lamesa II's 50 MW is 0% of that.

Solar plants in Texas around this size
PlantCountyMW2025 MWh
BrightsideBee5193,985
Pearl SolarPecos5097,375
SolaireHolman Solar ProjectBrewster50105,987
Lamesa IIDawson50120,697
BT Signal RanchHunt5099,664
Gransolar Texas One, LLCMilam50110,595
Pitts Dudik SolarHill50101,679