Solar power plant, Arizona
McFarland A Solar and Storage power plant, Arizona
McFarland A Solar and Storage is a 300 MW power plant, 200 MW of it solar, in Yuma County, Arizona, operated by AES Clean Energy, and it generated 542,282 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.5% of the generation reported in Arizona, and its capacity factor sits at the 95th percentile of U.S. solar plants. By 2025 generation it ranks 1,263rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the McFarland A Solar and Storage plant run compared with other solar plants?
The McFarland A Solar and Storage plant's solar units had a capacity factor of 31% in 2025 on 200 MW of net summer capacity, the 95th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 115 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| McFarland A Solar and Storage | 31% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does, for its solar generators only. Values above 105% are left out of the comparison.
Is the McFarland A Solar and Storage plant generating more or less than last year?
Generation at McFarland A Solar and Storage rose 15.9% from 2024 to 2025, from 467,733 MWh to 542,282 MWh. Through August 2026 it is running 2.5% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 467,733 |
| 2025 | 542,282 |
| 2026 through August | 382,088 |
| 2025, same months | 391,940 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 53,370 |
| July 2026 | 55,091 |
| June 2026 | 59,871 |
| May 2026 | 64,095 |
| April 2026 | 42,751 |
| March 2026 | 43,370 |
| February 2026 | 32,804 |
| January 2026 | 30,736 |
| December 2025 | 28,247 |
| November 2025 | 31,340 |
| October 2025 | 44,368 |
| September 2025 | 46,387 |
| August 2025 | 57,448 |
| July 2025 | 63,169 |
| June 2025 | 66,043 |
| May 2025 | 50,721 |
| April 2025 | 58,256 |
| March 2025 | 43,428 |
| February 2025 | 19,831 |
| January 2025 | 33,044 |
| December 2024 | 18,348 |
| November 2024 | 31,318 |
| October 2024 | 39,598 |
| September 2024 | 53,904 |
| August 2024 | 54,588 |
| July 2024 | 60,765 |
| June 2024 | 47,640 |
| May 2024 | 44,467 |
| April 2024 | 41,677 |
| March 2024 | 17,154 |
| February 2024 | 30,219 |
| January 2024 | 28,055 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the McFarland A Solar and Storage plant, and when do they retire?
2 operable generators total 300 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 2 | 300 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| BESS | Operating | Batteries | 100 | 2023 | n/a |
| MCFRA | Operating | Solar Photovoltaic | 200 | 2023 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the McFarland A Solar and Storage plant?
EIA lists no joint owners for McFarland A Solar and Storage. AES Clean Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
What fuels does the McFarland A Solar and Storage plant use?
McFarland A Solar and Storage has capacity on 2 fuels: 67% solar and 33% battery and pumped storage. In 2025, solar made 102% of its output.
| Fuel | MW | Share | 2025 MWh |
|---|---|---|---|
| Solar | 200 | 66.7% | 550,669 |
| Battery and pumped storage | 100 | 33.3% | -8,387 |
Source: EIA Forms EIA-860 and EIA-923, 2025.
Where is the McFarland A Solar and Storage plant?
McFarland A Solar and Storage is in Dateland, Yuma County, Arizona, at 32.9513° N, 113.4905° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Arizona are similar in size?
Arizona has 111 operable solar plants with 6,672 MW of capacity, and McFarland A Solar and Storage's 200 MW is 3% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Solana Generating Station | Maricopa | 280 | 845,906 |
| Roadrunner Solar and BESS | Cochise | 235 | 32,947 |
| Sun Streams 3 | Maricopa | 215 | 532,548 |
| McFarland A Solar and Storage | Yuma | 200 | 550,669 |
| Brittlebush Solar | Pinal | 200 | 562,100 |
| White Wing Solar | Yuma | 179 | 453,960 |
| Mesquite Solar 1 | Maricopa | 170 | 392,193 |
Source: EIA Forms EIA-860 and EIA-923, 2025.