Solar power plant, California
Mustang Two solar power plant, California
Mustang Two is a 150 MW solar power plant in Kings County, California, operated by RE Mustang Two LLC, and it generated 396,295 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in California, and its capacity factor sits at the 92nd percentile of U.S. solar plants. By 2025 generation it ranks 1,602nd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Mustang Two plant run compared with other solar plants?
The Mustang Two plant had a capacity factor of 30% in 2025 on 150 MW of net summer capacity, the 92nd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 110 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Mustang Two | 30% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Mustang Two plant generating more or less than last year?
Generation at Mustang Two rose 3.2% from 2024 to 2025, from 384,133 MWh to 396,295 MWh. Through August 2026 it is running 71.7% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 384,133 |
| 2025 | 396,295 |
| 2026 through August | 87,591 |
| 2025, same months | 309,813 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 0 |
| July 2026 | 0 |
| June 2026 | 0 |
| May 2026 | 0 |
| April 2026 | 13,313 |
| March 2026 | 36,505 |
| February 2026 | 21,478 |
| January 2026 | 16,295 |
| December 2025 | 7,671 |
| November 2025 | 14,807 |
| October 2025 | 30,301 |
| September 2025 | 33,703 |
| August 2025 | 45,911 |
| July 2025 | 52,021 |
| June 2025 | 49,870 |
| May 2025 | 50,842 |
| April 2025 | 39,524 |
| March 2025 | 27,664 |
| February 2025 | 21,435 |
| January 2025 | 22,546 |
| December 2024 | 14,120 |
| November 2024 | 20,469 |
| October 2024 | 28,398 |
| September 2024 | 37,370 |
| August 2024 | 42,359 |
| July 2024 | 45,735 |
| June 2024 | 47,584 |
| May 2024 | 44,666 |
| April 2024 | 39,917 |
| March 2024 | 32,414 |
| February 2024 | 17,662 |
| January 2024 | 13,439 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Mustang Two plant, and when do they retire?
2 operable generators total 150 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 2 | 150 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| M2BAR | Operating | Solar Photovoltaic | 50 | 2020 | n/a |
| M2WHI | Operating | Solar Photovoltaic | 100 | 2020 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Mustang Two plant?
Idemitsu Renewables is the only joint owner reported for Mustang Two, with 100.0%. RE Mustang Two LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Mustang Two plant?
Mustang Two is in Lemoore, Kings County, California, at 36.2168° N, 119.8964° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Mustang Two's 150 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| North Rosamond Solar LLC | Kern | 151 | 397,173 |
| Chestnut | Kings | 151 | 403,005 |
| CA Flats Solar 150, LLC | San Luis Obispo | 150 | 305,407 |
| Mustang Two | Kings | 150 | 396,295 |
| Fifth Standard Solar PV, LLC (Hybrid) | Fresno | 150 | 327,093 |
| Baldy Mesa Solar & Storage | San Bernardino | 150 | 303,251 |
| Northern Orchard Solar PV, LLC | Kern | 150 | 210,871 |
Source: EIA Forms EIA-860 and EIA-923, 2025.