Hydro power plant, Washington
Packwood hydroelectric power plant, Washington
Packwood is a 27.5 MW hydro power plant in Lewis County, Washington, operated by Energy Northwest-Packwood, and it generated 73,848 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Washington, and its capacity factor sits at the 49th percentile of U.S. hydro plants. By 2025 generation it ranks 3,717th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Packwood plant run compared with other hydro plants?
The Packwood plant had a capacity factor of 32% in 2025 on 26 MW of net summer capacity, the 49th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 118 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Packwood | 32% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Packwood plant generating more or less than last year?
Packwood generated 73,848 MWh in 2025; EIA reports no 2024 total to compare. 2024 has output for only 11 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 62,999 |
| 2025 | 73,848 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 13,012 |
| November 2025 | 9,535 |
| October 2025 | 1,750 |
| September 2025 | 1,160 |
| August 2025 | 0 |
| July 2025 | 4,410 |
| June 2025 | 9,831 |
| May 2025 | 9,705 |
| April 2025 | 8,080 |
| March 2025 | 7,581 |
| February 2025 | 4,115 |
| January 2025 | 4,669 |
| December 2024 | 5,166 |
| November 2024 | 1,020 |
| October 2024 | 2,056 |
| September 2024 | 3,614 |
| August 2024 | 0 |
| July 2024 | 5,790 |
| June 2024 | 13,587 |
| May 2024 | 9,239 |
| April 2024 | 4,552 |
| March 2024 | 3,814 |
| February 2024 | 6,484 |
| January 2024 | 7,677 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Packwood plant, and when do they retire?
1 operable generator totals 27.5 MW, with an average age of 61 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1960s | 1 | 28 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 28 | 1964 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Packwood plant?
EIA lists no joint owners for Packwood. Energy Northwest-Packwood operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Packwood plant?
Packwood is in Packwood, Lewis County, Washington, at 46.5958° N, 121.5694° W. It sits in the Bonneville Power Administration balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Washington are similar in size?
Washington has 73 operable hydro plants with 21,462 MW of capacity, and Packwood's 27.5 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Snoqualmie 2 | King | 39 | 106,754 |
| Nine Mile | Spokane | 38 | 132,210 |
| Cedar Falls (WA) | King | 30 | 53,629 |
| Packwood | Lewis | 28 | 73,848 |
| Main Canal Headworks | Grant | 27 | 105,240 |
| Twin Falls Hydro | King | 24 | 59,297 |
| Electron | Pierce | 23 | 0 |
Source: EIA Forms EIA-860 and EIA-923, 2025.