Skip to main content
RateWatt

Solar power plant, Mississippi

Pearl River Solar Park LLC power plant, Mississippi

Pearl River Solar Park LLC is a 175 MW solar power plant in Scott County, Mississippi, operated by Pearl River Solar Park, LLC, and it generated 418,916 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.5% of the generation reported in Mississippi, and its capacity factor sits at the 79th percentile of U.S. solar plants. By 2025 generation it ranks 1,535th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

175 MWNameplate capacity
27%Capacity factor, 2025, 79th percentile, on 175 MW net summer
0.5%Of MS generation, 2025
1 yearAverage generator age, by MW

How hard does the Pearl River Solar Park LLC plant run compared with other solar plants?

The Pearl River Solar Park LLC plant had a capacity factor of 27% in 2025 on 175 MW of net summer capacity, the 79th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 100 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Pearl River Solar Park LLC27%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Pearl River Solar Park LLC plant generating more or less than last year?

Pearl River Solar Park LLC generated 418,916 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 5.3% ahead of the same months of 2025. 2024 has output for only 10 months, so the two years are not compared.

Net generation by period
PeriodMWh
2024304,816
2025418,916
2026 through August307,164
2025, same months291,604
Monthly generation, Mar 2024 to Aug 2026
MonthMWh
August 202646,539
July 202648,552
June 202640,387
May 202639,921
April 202640,630
March 202640,829
February 202627,665
January 202622,641
December 202520,658
November 202528,182
October 202536,049
September 202542,423
August 202535,087
July 202548,156
June 202545,620
May 202536,305
April 202540,607
March 202537,011
February 202523,902
January 202524,916
December 202424,048
November 202425,456
October 202443,502
September 202433,911
August 202446,791
July 202439,170
June 202435,405
May 202428,759
April 202413,181
March 202414,593

Source: EIA Form EIA-923, through August 2026.

How much of Mississippi's electricity comes from the Pearl River Solar Park LLC plant?

Pearl River Solar Park LLC made 0.5% of the 77,727,245 MWh reported by Mississippi plants in 2025, from 1.0% of the state's 17,862 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 23rd largest of 63 plants in Mississippi, the 1,781st largest of 14,327 in the U.S. and the 225th largest of 7,223 solar plants. By 2025 generation it is the 21st largest of 57 generating plants in the state.

Pearl River Solar Park LLC within Mississippi, 2025
MeasureThis plantMississippiShare
Capacity (MW)17517,8621.0%
Generation (MWh)418,91677,727,2450.5%
Solar capacity (MW)1751,52411.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Pearl River Solar Park LLC plant, and when do they retire?

1 operable generator totals 175 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1175100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN01OperatingSolar Photovoltaic1752024n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Pearl River Solar Park LLC plant?

EIA lists no joint owners for Pearl River Solar Park LLC. Pearl River Solar Park, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Pearl River Solar Park LLC plant?

Pearl River Solar Park LLC is in Morton, Scott County, Mississippi, at 32.5510° N, 89.7301° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Mississippi are similar in size?

Mississippi has 25 operable solar plants with 1,524 MW of capacity, and Pearl River Solar Park LLC's 175 MW is 11% of that.

Solar plants in Mississippi around this size
PlantCountyMW2025 MWh
Golden TriangleLowndes200418,711
Pearl River Solar Park LLCScott175418,916
Golden Triangle IILowndes150325,338
Sunflower CountySunflower100154,825
Ragsdale Solar LLCMadison100238,898