Skip to main content
RateWatt

Solar power plant, Michigan

Pine River Solar Park power plant, Michigan

Pine River Solar Park is a 80 MW solar power plant in Gratiot County, Michigan, operated by DTE Electric Company, and it generated 78,143 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Michigan, and its capacity factor sits at the 8th percentile of U.S. solar plants. By 2025 generation it ranks 3,665th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

80 MWNameplate capacity
11%Capacity factor, 2025, 8th percentile, on 80 MW net summer
0.1%Of MI generation, 2025
Under 1 yearAverage generator age, by MW

How hard does the Pine River Solar Park plant run compared with other solar plants?

The Pine River Solar Park plant had a capacity factor of 11% in 2025 on 80 MW of net summer capacity, the 8th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 41 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Pine River Solar Park11%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Pine River Solar Park plant generating more or less than last year?

Pine River Solar Park generated 78,143 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 82.4% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024n/a
202578,143
2026 through August102,841
2025, same months56,380
Monthly generation, Jun 2025 to Aug 2026
MonthMWh
August 202615,738
July 202621,243
June 202618,332
May 202617,830
April 202611,559
March 20268,967
February 20267,005
January 20262,167
December 20254,249
November 20256,520
October 202512
September 202510,982
August 202519,009
July 202518,909
June 202518,462

Source: EIA Form EIA-923, through August 2026.

How much of Michigan's electricity comes from the Pine River Solar Park plant?

Pine River Solar Park made 0.1% of the 127,929,498 MWh reported by Michigan plants in 2025, from 0.2% of the state's 34,725 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 63rd largest of 283 plants in Michigan, the 2,965th largest of 14,327 in the U.S. and the 562nd largest of 7,223 solar plants. By 2025 generation it is the 88th largest of 261 generating plants in the state.

Pine River Solar Park within Michigan, 2025
MeasureThis plantMichiganShare
Capacity (MW)8034,7250.2%
Generation (MWh)78,143127,929,4980.1%
Solar capacity (MW)801,9674.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Pine River Solar Park plant, and when do they retire?

1 operable generator totals 80 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s180100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
PNRSPOperatingSolar Photovoltaic802025n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Pine River Solar Park plant?

EIA lists no joint owners for Pine River Solar Park. DTE Electric Company operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does DTE Electric Company charge homes?

DTE Electric Company, the operator of Pine River Solar Park, had an average residential price of 20.25¢ per kWh and an average bill of $126 a month in 2025, 1% above the Michigan average of 20.03¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Michigan
DTE Electric Company20.25¢$1261% higher
Michigan average20.03¢$127
U.S. average17.23¢$15114% lower

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Pine River Solar Park plant?

Pine River Solar Park is in Alma, Gratiot County, Michigan, at 43.4312° N, 84.6836° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region RFC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Michigan are similar in size?

Michigan has 70 operable solar plants with 1,967 MW of capacity, and Pine River Solar Park's 80 MW is 4% of that.

Solar plants in Michigan around this size
PlantCountyMW2025 MWh
Assembly Solar II LLCShiawassee110225,905
Cereal City Solar, LLCCalhoun100196,187
Polaris Solar ParkGratiot10058,951
Pine River Solar ParkGratiot8078,143
Assembly Solar IIIShiawassee79164,992
Assembly Solar ProjectShiawassee5099,840
Genesee Solar ProjectGenesee411,046

Source: EIA Forms EIA-860 and EIA-923, 2025.