Rambler solar power plant, Texas

Rambler is a 200 MW solar power plant in Tom Green County, Texas, operated by Deriva Energy, and it generated 376,921 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 38th percentile of U.S. solar plants. By 2025 generation it ranks 1,666th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

200 MWNameplate capacity
22%Capacity factor, 2025, 38th percentile, on 200 MW net summer
0.1%Of TX generation, 2025
5 yearsAverage generator age, by MW

How hard does the Rambler plant run compared with other solar plants?

The Rambler plant had a capacity factor of 22% in 2025 on 200 MW of net summer capacity, the 38th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 79 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Rambler22%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Rambler plant generating more or less than last year?

Generation at Rambler fell 14.3% from 2024 to 2025, from 439,864 MWh to 376,921 MWh. Through August 2026 it is running 6.9% behind the same months of 2025.

Net generation by period
PeriodMWh
2024439,864
2025376,921
2026 through August237,839
2025, same months255,356
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202638,820
July 202644,522
June 202635,573
May 202626,011
April 202624,687
March 202621,325
February 202625,787
January 202621,114
December 202525,101
November 202522,948
October 202530,049
September 202543,467
August 202540,803
July 202534,531
June 202552,843
May 202531,985
April 202515,563
March 202530,151
February 202525,825
January 202523,655
December 202421,710
November 202427,381
October 202437,002
September 202442,192
August 202454,471
July 202452,807
June 202449,008
May 202441,352
April 202429,318
March 202434,649
February 202427,307
January 202422,667

Source: EIA Form EIA-923, through August 2026.

How much of Texas' electricity comes from the Rambler plant?

Rambler made 0.1% of the 592,896,176 MWh reported by Texas plants in 2025, from 0.1% of the state's 195,966 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 302nd largest of 1,023 plants in Texas, the 1,524th largest of 14,327 in the U.S. and the 143rd largest of 7,223 solar plants. By 2025 generation it is the 340th largest of 816 generating plants in the state.

Rambler within Texas, 2025
MeasureThis plantTexasShare
Capacity (MW)200195,9660.1%
Generation (MWh)376,921592,896,1760.1%
Solar capacity (MW)20030,7390.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Rambler plant, and when do they retire?

1 operable generator totals 200 MW, with an average age of 5 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1200100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
RMBLROperatingSolar Photovoltaic2002020n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Rambler plant?

RE Rambler, LLC is the only joint owner reported for Rambler, with 100.0%. Deriva Energy operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Rambler plant?

Rambler is in San Angelo, Tom Green County, Texas, at 31.5170° N, 100.6000° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Texas are similar in size?

Texas has 225 operable solar plants with 30,739 MW of capacity, and Rambler's 200 MW is 1% of that.

Solar plants in Texas around this size
PlantCountyMW2025 MWh
AP Sunray LLCUvalde204429,906
Cutlass Solar IIFort Bend203417,759
Holstein 1 Solar FarmNolan200255,203
RamblerTom Green200376,921
Samson Solar Energy II LLCLamar200353,525
ANSON Solar Center, LLCJones200503,715
Big Star Solar, LLC (Hybrid)Bastrop200376,255

Source: EIA Forms EIA-860 and EIA-923, 2025.