Wind power plant, Texas
Route 66 Wind Plant, Texas
Route 66 Wind Plant is a 150 MW wind power plant in Carson County, Texas, operated by Onward Energy, and it generated 552,481 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Texas, and its capacity factor sits at the 82nd percentile of U.S. wind plants. By 2025 generation it ranks 1,231st of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does Route 66 Wind Plant run compared with other wind plants?
Route 66 Wind Plant had a capacity factor of 42% in 2025 on 150 MW of net summer capacity, the 82nd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 153 days at full output out of 365.
0%Shaded: the middle half of wind plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Route 66 Wind Plant | 42% |
| Wind plants, 75th percentile | 41% |
| Wind plants, median | 33% |
| Wind plants, 25th percentile | 26% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is Route 66 Wind Plant generating more or less than last year?
Generation at Route 66 Wind Plant fell 9.2% from 2024 to 2025, from 608,174 MWh to 552,481 MWh.
| Period | MWh |
|---|---|
| 2024 | 608,174 |
| 2025 | 552,481 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 45,330 |
| November 2025 | 48,403 |
| October 2025 | 46,623 |
| September 2025 | 47,023 |
| August 2025 | 45,520 |
| July 2025 | 45,511 |
| June 2025 | 47,477 |
| May 2025 | 43,968 |
| April 2025 | 36,844 |
| March 2025 | 43,547 |
| February 2025 | 49,739 |
| January 2025 | 52,496 |
| December 2024 | 48,490 |
| November 2024 | 35,098 |
| October 2024 | 52,749 |
| September 2024 | 44,112 |
| August 2024 | 47,390 |
| July 2024 | 54,426 |
| June 2024 | 61,425 |
| May 2024 | 60,879 |
| April 2024 | 47,959 |
| March 2024 | 48,695 |
| February 2024 | 55,383 |
| January 2024 | 51,568 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at Route 66 Wind Plant, and when do they retire?
1 operable generator totals 150 MW, with an average age of 10 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 150 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| RT661 | Operating | Onshore Wind Turbine | 150 | 2015 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns Route 66 Wind Plant?
EIA lists no joint owners for Route 66 Wind Plant. Onward Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is Route 66 Wind Plant?
Route 66 Wind Plant is in Panhandle, Carson County, Texas, at 35.2053° N, 101.4342° W. It sits in the Electric Reliability Council of Texas, Inc. balancing area (NERC region TRE).
Source: EIA Form EIA-860, Plant, 2025 final.
Which wind plants in Texas are similar in size?
Texas has 228 operable wind plants with 43,942 MW of capacity, and Route 66 Wind Plant's 150 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Loraine Windpark Project LLC | Mitchell | 150 | 327,923 |
| Senate Wind LLC | Jack | 150 | 393,732 |
| Goldthwaite Wind Energy Facility | Mills | 150 | 408,631 |
| Route 66 Wind Plant | Carson | 150 | 552,481 |
| Green Pastures Wind I | Baylor | 150 | 255,605 |
| Green Pastures Wind II | Knox | 150 | 298,081 |
| Briscoe Wind Farm | Briscoe | 150 | 420,754 |
Source: EIA Forms EIA-860 and EIA-923, 2025.