Sapphire Sky Wind Energy LLC power plant, Illinois

Sapphire Sky Wind Energy LLC is a 260 MW wind power plant in DeWitt County, Illinois, operated by Invenergy Services LLC, and it generated 925,776 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.5% of the generation reported in Illinois, and its capacity factor sits at the 75th percentile of U.S. wind plants. By 2025 generation it ranks 774th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

260 MWNameplate capacity
41%Capacity factor, 2025, 75th percentile, on 260 MW net summer
0.5%Of IL generation, 2025
2 yearsAverage generator age, by MW

How hard does the Sapphire Sky Wind Energy LLC plant run compared with other wind plants?

The Sapphire Sky Wind Energy LLC plant had a capacity factor of 41% in 2025 on 260 MW of net summer capacity, the 75th percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 148 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Sapphire Sky Wind Energy LLC41%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Sapphire Sky Wind Energy LLC plant generating more or less than last year?

Generation at Sapphire Sky Wind Energy LLC fell 2.6% from 2024 to 2025, from 950,734 MWh to 925,776 MWh. Through August 2026 it is running 7.2% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024950,734
2025925,776
2026 through August653,119
2025, same months609,281
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202640,273
July 202636,817
June 202660,634
May 202675,917
April 2026122,620
March 2026122,045
February 202681,534
January 2026113,279
December 2025103,799
November 202593,704
October 202586,230
September 202532,762
August 202537,967
July 202532,400
June 202555,041
May 202581,905
April 202591,795
March 2025123,181
February 202593,125
January 202593,867
December 2024108,298
November 2024100,609
October 202486,263
September 202447,341
August 202444,368
July 202441,575
June 202480,035
May 202465,508
April 202485,332
March 2024109,513
February 202494,615
January 202487,277

Source: EIA Form EIA-923, through August 2026.

How much of Illinois' electricity comes from the Sapphire Sky Wind Energy LLC plant?

Sapphire Sky Wind Energy LLC made 0.5% of the 191,710,915 MWh reported by Illinois plants in 2025, from 0.5% of the state's 52,515 MW of capacity. By capacity it is the 47th largest of 602 plants in Illinois, the 1,207th largest of 14,327 in the U.S. and the 128th largest of 1,358 wind plants. By 2025 generation it is the 20th largest of 531 generating plants in the state.

Sapphire Sky Wind Energy LLC within Illinois, 2025
MeasureThis plantIllinoisShare
Capacity (MW)26052,5150.5%
Generation (MWh)925,776191,710,9150.5%
Wind capacity (MW)2608,4583.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Sapphire Sky Wind Energy LLC plant, and when do they retire?

1 operable generator totals 260 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s1260100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
65011OperatingOnshore Wind Turbine2602023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Sapphire Sky Wind Energy LLC plant?

2 owners report shares in Sapphire Sky Wind Energy LLC; WEC Energy Group holds the largest named share, 90.0% or about 234 MW. Invenergy Services LLC operates the plant.

Reported ownership of operable capacity
OwnerShareMW2025 MWh, by share
WEC Energy Group90.0%234833,198
Invenergy Services LLC10.0%2692,578

Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.

Where is the Sapphire Sky Wind Energy LLC plant?

Sapphire Sky Wind Energy LLC is in Farmer City, DeWitt County, Illinois, at 40.2945° N, 88.5846° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Illinois are similar in size?

Illinois has 55 operable wind plants with 8,458 MW of capacity, and Sapphire Sky Wind Energy LLC's 260 MW is 3% of that.

Wind plants in Illinois around this size
PlantCountyMW2025 MWh
Streator Cayuga Ridge SouthLivingston300676,201
Prosperity WindPiatt300678,212
Radfords Run Wind FarmDewitt2781,147,008
Sapphire Sky Wind Energy LLCDeWitt260925,776
Blooming Grove Wind Energy CenterLivingston250866,027
Big Sky Wind LLCBureau239816,633
FPL Energy Illinois Wind LLC HybridDeKalb218632,162