Hydro power plant, Wyoming
Seminoe hydroelectric power plant, Wyoming
Seminoe is a 51.6 MW hydro power plant in Carbon County, Wyoming, operated by U S Bureau of Reclamation, and it generated 84,528 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Wyoming, and its capacity factor sits at the 18th percentile of U.S. hydro plants. By 2025 generation it ranks 3,589th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Seminoe plant run compared with other hydro plants?
The Seminoe plant had a capacity factor of 19% in 2025 on 51.6 MW of net summer capacity, the 18th percentile of the 427 U.S. hydro plants with at least 20 MW. The typical hydro plant reached 33%. That equals about 68 days at full output out of 365.
0%Shaded: the middle half of hydro plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Seminoe | 19% |
| Hydro plants, 75th percentile | 44% |
| Hydro plants, median | 33% |
| Hydro plants, 25th percentile | 22% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Seminoe plant generating more or less than last year?
Generation at Seminoe fell 38.3% from 2024 to 2025, from 136,952 MWh to 84,528 MWh.
| Period | MWh |
|---|---|
| 2024 | 136,952 |
| 2025 | 84,528 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 3,731 |
| November 2025 | 3,600 |
| October 2025 | 3,562 |
| September 2025 | 3,435 |
| August 2025 | 3,513 |
| July 2025 | 9,587 |
| June 2025 | 13,773 |
| May 2025 | 21,608 |
| April 2025 | 9,500 |
| March 2025 | 4,163 |
| February 2025 | 3,818 |
| January 2025 | 4,238 |
| December 2024 | 4,180 |
| November 2024 | 3,664 |
| October 2024 | 4,130 |
| September 2024 | 4,234 |
| August 2024 | 18,604 |
| July 2024 | 25,231 |
| June 2024 | 25,252 |
| May 2024 | 25,307 |
| April 2024 | 14,230 |
| March 2024 | 4,057 |
| February 2024 | 3,865 |
| January 2024 | 4,198 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Seminoe plant, and when do they retire?
3 operable generators total 51.6 MW, with an average age of 86 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 1930s | 3 | 52 | 100% | none reported |
Every generator, 3 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| 1 | Operating | Conventional Hydroelectric | 17 | 1939 | n/a |
| 2 | Operating | Conventional Hydroelectric | 17 | 1939 | n/a |
| 3 | Operating | Conventional Hydroelectric | 17 | 1939 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Seminoe plant?
EIA lists no joint owners for Seminoe. U S Bureau of Reclamation operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Seminoe plant?
Seminoe is in Sinclair, Carbon County, Wyoming, at 42.1561° N, 106.9085° W. It sits in the Western Area Power Administration UGP West balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which hydro plants in Wyoming are similar in size?
Wyoming has 16 operable hydro plants with 303 MW of capacity, and Seminoe's 51.6 MW is 17% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Fremont Canyon | Natrona | 67 | 233,507 |
| Seminoe | Carbon | 52 | 84,528 |
| Alcova | Natrona | 41 | 107,154 |
| Glendo | Platte | 38 | 67,348 |
| Kortes | Carbon | 36 | 105,700 |
Source: EIA Forms EIA-860 and EIA-923, 2025.