Solar power plant, California
Solar Borrego I power plant, California
Solar Borrego I is a 26 MW solar power plant in San Diego County, California, operated by NRG Solar Borrego I, and it generated 61,307 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 77th percentile of U.S. solar plants. By 2025 generation it ranks 3,857th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Solar Borrego I plant run compared with other solar plants?
The Solar Borrego I plant had a capacity factor of 27% in 2025 on 26 MW of net summer capacity, the 77th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 98 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Solar Borrego I | 27% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Solar Borrego I plant generating more or less than last year?
Generation at Solar Borrego I fell 1.4% from 2024 to 2025, from 62,170 MWh to 61,307 MWh.
| Period | MWh |
|---|---|
| 2024 | 62,170 |
| 2025 | 61,307 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 3,118 |
| November 2025 | 3,401 |
| October 2025 | 4,638 |
| September 2025 | 4,895 |
| August 2025 | 6,451 |
| July 2025 | 7,721 |
| June 2025 | 6,063 |
| May 2025 | 6,934 |
| April 2025 | 6,230 |
| March 2025 | 4,598 |
| February 2025 | 3,789 |
| January 2025 | 3,469 |
| December 2024 | 3,162 |
| November 2024 | 3,474 |
| October 2024 | 4,858 |
| September 2024 | 5,773 |
| August 2024 | 6,785 |
| July 2024 | 7,209 |
| June 2024 | 7,263 |
| May 2024 | 6,749 |
| April 2024 | 5,907 |
| March 2024 | 4,228 |
| February 2024 | 3,379 |
| January 2024 | 3,383 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Solar Borrego I plant, and when do they retire?
1 operable generator totals 26 MW, with an average age of 12 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 26 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| SB1 | Operating | Solar Photovoltaic | 26 | 2013 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Solar Borrego I plant?
EIA lists no joint owners for Solar Borrego I. NRG Solar Borrego I operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Solar Borrego I plant?
Solar Borrego I is in Borrego Springs, San Diego County, California, at 33.2989° N, 116.3508° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Solar Borrego I's 26 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Chevron - Lost Hills Hybrid | Kern | 30 | 65,771 |
| Edwards Sanborn E3 | Kern | 27 | 57,391 |
| Hayworth Solar | Kern | 27 | 46,989 |
| Solar Borrego I | San Diego | 26 | 61,307 |
| Vandenberg Solar Project | Santa Barbara | 25 | 39,494 |
| Axium Modesto Solar | Stanislaus | 25 | 53,191 |
| Imperial Valley Solar Company 1 LLC | Imperial | 23 | 33,146 |
Source: EIA Forms EIA-860 and EIA-923, 2025.