Skip to main content
RateWatt

Natural gas power plant, California

Tracy Combined Cycle Power Plant, California

Tracy Combined Cycle Power Plant is a 336 MW natural gas power plant in San Joaquin County, California, operated by MRP San Joaquin Energy LLC., and it generated 896,191 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in California, and its capacity factor sits at the 59th percentile of U.S. natural gas plants. By 2025 generation it ranks 798th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

336 MWNameplate capacity
32%Capacity factor, 2025, 59th percentile, on 320 MW net summer
0.4%Of CA generation, 2025
18 yearsAverage generator age, by MW

How hard does Tracy Combined Cycle Power Plant run compared with other natural gas plants?

Tracy Combined Cycle Power Plant had a capacity factor of 32% in 2025 on 320 MW of net summer capacity, the 59th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 117 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Tracy Combined Cycle Power Plant32%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is Tracy Combined Cycle Power Plant generating more or less than last year?

Generation at Tracy Combined Cycle Power Plant fell 10.4% from 2024 to 2025, from 1,000,454 MWh to 896,191 MWh. Through August 2026 it is running 44.7% behind the same months of 2025.

Net generation by period
PeriodMWh
20241,000,454
2025896,191
2026 through August297,340
2025, same months537,456
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 2026100,388
July 202674,742
June 202622,760
May 20267,773
April 202612,656
March 202611,644
February 202620,098
January 202647,279
December 202562,678
November 2025122,766
October 202566,919
September 2025106,372
August 2025113,394
July 202560,888
June 202565,121
May 202547,106
April 202541,866
March 202586,421
February 202520,410
January 2025102,250
December 2024112,727
November 2024136,379
October 2024118,198
September 202473,098
August 202478,156
July 2024125,232
June 202443,305
May 202433,465
April 202434,605
March 202433,503
February 202486,083
January 2024125,703

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from Tracy Combined Cycle Power Plant?

Tracy Combined Cycle Power Plant made 0.4% of the 204,542,898 MWh reported by California plants in 2025, from 0.3% of the state's 107,433 MW of capacity. Its share of output is 1.4 times its share of capacity. By capacity it is the 64th largest of 1,877 plants in California, the 960th largest of 14,327 in the U.S. and the 577th largest of 1,962 natural gas plants. By 2025 generation it is the 37th largest of 1,608 generating plants in the state.

Tracy Combined Cycle Power Plant within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)336107,4330.3%
Generation (MWh)896,191204,542,8980.4%
Natural gas capacity (MW)33640,2110.8%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at Tracy Combined Cycle Power Plant, and when do they retire?

3 operable generators total 336 MW, with an average age of 18 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2000s216950%none reported
2010s116750%none reported
Every generator, 3 in all
UnitStatusTechnologyMWIn servicePlanned retirement
TPP1OperatingNatural Gas Fired Combined Cycle842003n/a
TPP2OperatingNatural Gas Fired Combined Cycle842003n/a
TCC1OperatingNatural Gas Fired Combined Cycle1672012n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns Tracy Combined Cycle Power Plant?

EIA lists no joint owners for Tracy Combined Cycle Power Plant. MRP San Joaquin Energy LLC. operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is Tracy Combined Cycle Power Plant?

Tracy Combined Cycle Power Plant is in Tracy, San Joaquin County, California, at 37.7107° N, 121.4906° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in California are similar in size?

California has 304 operable natural gas plants with 40,211 MW of capacity, and Tracy Combined Cycle Power Plant's 336 MW is 1% of that.

Natural gas plants in California around this size
PlantCountyMW2025 MWh
Pio Pico Energy CenterSan Diego39546,864
Magnolia Power ProjectLos Angeles3881,204,502
El Centro HybridImperial3581,093,177
Tracy Combined Cycle Power PlantSan Joaquin336896,191
Los Esteros Critical Energy CenterSanta Clara306156,503
Walnut Energy CenterStanislaus3011,604,800
Kern River CogenerationKern300112,424

Source: EIA Forms EIA-860 and EIA-923, 2025.