Weston RICE is a 132 MW natural gas power plant in Marathon County, Wisconsin, operated by Wisconsin Public Service Corp, and it generated 144,470 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Wisconsin, and its capacity factor sits at the 39th percentile of U.S. natural gas plants. By 2025 generation it ranks 2,959th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

132 MWNameplate capacity
13%Capacity factor, 2025, 39th percentile, on 132 MW net summer
0.2%Of WI generation, 2025
2 yearsAverage generator age, by MW

How hard does the Weston RICE plant run compared with other natural gas plants?

The Weston RICE plant had a capacity factor of 13% in 2025 on 132 MW of net summer capacity, the 39th percentile of the 1,236 U.S. natural gas plants with at least 20 MW. The typical natural gas plant reached 22%. That equals about 46 days at full output out of 365.

0%Shaded: the middle half of natural gas plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Weston RICE13%
Natural gas plants, 75th percentile56%
Natural gas plants, median22%
Natural gas plants, 25th percentile6%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Weston RICE plant generating more or less than last year?

Generation at Weston RICE rose 69.0% from 2024 to 2025, from 85,471 MWh to 144,470 MWh.

Net generation by period
PeriodMWh
202485,471
2025144,470
Monthly generation, Jan 2024 to Dec 2025
MonthMWh
December 202513,635
November 202512,164
October 20259,631
September 202512,228
August 202516,200
July 202517,189
June 202515,168
May 20259,903
April 20256,796
March 20257,785
February 202510,921
January 202512,850
December 20247,533
November 20246,523
October 20245,503
September 20247,171
August 20248,339
July 20248,677
June 20248,180
May 20247,165
April 20244,743
March 20247,314
February 20246,512
January 20247,812

Source: EIA Form EIA-923, through August 2026.

How much of Wisconsin's electricity comes from the Weston RICE plant?

Weston RICE made 0.2% of the 66,249,756 MWh reported by Wisconsin plants in 2025, from 0.7% of the state's 19,442 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 35th largest of 273 plants in Wisconsin, the 2,199th largest of 14,327 in the U.S. and the 819th largest of 1,962 natural gas plants. By 2025 generation it is the 44th largest of 259 generating plants in the state.

Weston RICE within Wisconsin, 2025
MeasureThis plantWisconsinShare
Capacity (MW)13219,4420.7%
Generation (MWh)144,47066,249,7560.2%
Natural gas capacity (MW)1327,8241.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Weston RICE plant, and when do they retire?

7 operable generators total 132 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s7132100%none reported
Every generator, 7 in all
UnitStatusTechnologyMWIn servicePlanned retirement
W11OperatingNatural Gas Internal Combustion Engine192023n/a
W12OperatingNatural Gas Internal Combustion Engine192023n/a
W13OperatingNatural Gas Internal Combustion Engine192023n/a
W14OperatingNatural Gas Internal Combustion Engine192023n/a
W15OperatingNatural Gas Internal Combustion Engine192023n/a
W16OperatingNatural Gas Internal Combustion Engine192023n/a
W17OperatingNatural Gas Internal Combustion Engine192023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Weston RICE plant?

2 owners report shares in Weston RICE; Wisconsin Electric Power Co holds the largest named share, 50.0% or about 65.8 MW. Wisconsin Public Service Corp operates the plant.

Reported ownership of operable capacity
OwnerShareMW2025 MWh, by share
Wisconsin Electric Power Co50.0%6672,235
Wisconsin Public Service Corp50.0%6672,235

Source: EIA Form EIA-860, Owner, 2025 final. MW and MWh by share multiply the plant totals by each owner's percentage.

What does Wisconsin Public Service Corp charge homes?

Wisconsin Public Service Corp, the operator of Weston RICE, had an average residential price of 17.20¢ per kWh and an average bill of $106 a month in 2025, 5% below the Wisconsin average of 18.08¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Wisconsin
Wisconsin Public Service Corp17.20¢$1065% lower
Wisconsin average18.08¢$121
U.S. average17.23¢$1515% lower

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Weston RICE plant?

Weston RICE is in Kronenwetter, Marathon County, Wisconsin, at 44.8564° N, 89.6540° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region RFC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which natural gas plants in Wisconsin are similar in size?

Wisconsin has 38 operable natural gas plants with 7,824 MW of capacity, and Weston RICE's 132 MW is 2% of that.

Natural gas plants in Wisconsin around this size
PlantCountyMW2025 MWh
De Pere Energy CenterBrown192107,872
West MarinetteMarinette18790,259
West Campus Cogeneration FacilityDane169305,079
Weston RICEMarathon132144,470
Blount StreetDane10058,585
PulliamBrown91109,890
West Marinette 34Marinette8384,865