Anhinga Solar Energy Center, Florida

Anhinga Solar Energy Center is a 74.5 MW solar power plant in Clay County, Florida, operated by Florida Power & Light Co, and it generated 128,847 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 24th percentile of U.S. solar plants. By 2025 generation it ranks 3,112th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

74.5 MWNameplate capacity
20%Capacity factor, 2025, 24th percentile, on 74.5 MW net summer
3,112thU.S. rank by generation, 2025
2 yearsAverage generator age, by MW

How hard does the Anhinga Solar Energy Center plant run compared with other solar plants?

The Anhinga Solar Energy Center plant had a capacity factor of 20% in 2025 on 74.5 MW of net summer capacity, the 24th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 72 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Anhinga Solar Energy Center20%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Anhinga Solar Energy Center plant generating more or less than last year?

Generation at Anhinga Solar Energy Center rose 0.3% from 2024 to 2025, from 128,441 MWh to 128,847 MWh. Through August 2026 it is running 1.4% ahead of the same months of 2025.

Net generation by period
PeriodMWh
2024128,441
2025128,847
2026 through August94,081
2025, same months92,762
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202611,999
July 202613,471
June 202613,257
May 202613,353
April 202613,294
March 202612,249
February 20268,622
January 20267,836
December 20256,852
November 20259,575
October 20258,936
September 202510,722
August 202511,600
July 202512,268
June 202512,342
May 202513,636
April 202514,889
March 202512,554
February 20258,035
January 20257,438
December 20246,733
November 20248,136
October 20249,804
September 20248,086
August 202411,593
July 202411,333
June 202414,889
May 202415,637
April 202414,973
March 202410,993
February 20249,231
January 20247,033

Source: EIA Form EIA-923, through August 2026.

How much of Florida's electricity comes from the Anhinga Solar Energy Center plant?

Anhinga Solar Energy Center made 0.0% of the 267,867,735 MWh reported by Florida plants in 2025, from 0.1% of the state's 79,936 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 105th largest of 331 plants in Florida, the 3,163rd largest of 14,327 in the U.S. and the 690th largest of 7,223 solar plants. By 2025 generation it is the 200th largest of 313 generating plants in the state.

Anhinga Solar Energy Center within Florida, 2025
MeasureThis plantFloridaShare
Capacity (MW)7579,9360.1%
Generation (MWh)128,847267,867,7350.0%
Solar capacity (MW)7512,2230.6%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Anhinga Solar Energy Center plant, and when do they retire?

1 operable generator totals 74.5 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s175100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingSolar Photovoltaic752023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Anhinga Solar Energy Center plant?

EIA lists no joint owners for Anhinga Solar Energy Center. Florida Power & Light Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does Florida Power & Light Co charge homes?

Florida Power & Light Co, the operator of Anhinga Solar Energy Center, had an average residential price of 14.62¢ per kWh and an average bill of $162 a month in 2025, 4% below the Florida average of 15.21¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Florida
Florida Power & Light Co14.62¢$1624% lower
Florida average15.21¢$168
U.S. average17.23¢$15113% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Anhinga Solar Energy Center plant?

Anhinga Solar Energy Center is in Green Cove Springs, Clay County, Florida, at 29.8821° N, 81.6762° W. It sits in the Florida Power & Light Company balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Florida are similar in size?

Florida has 210 operable solar plants with 12,223 MW of capacity, and Anhinga Solar Energy Center's 74.5 MW is 1% of that.

Solar plants in Florida around this size
PlantCountyMW2025 MWh
Pink Trial Solar Energy CenterSt Lucie75147,447
FPL Shirer Branch Solar Energy CenterCalhoun75185,167
Wild Azalea Solar Energy CenterGadsden75173,333
Anhinga Solar Energy CenterClay75128,847
ApalacheeJackson75143,666
Blackwater River Solar Energy CenterSanta Rosa75141,274
FPL Cavendish Solar Energy CenterOkeechobee75116,139

Source: EIA Forms EIA-860 and EIA-923, 2025.