Skip to main content
RateWatt

Solar power plant, California

Beacon Solar Plant Site 2 power plant, California

Beacon Solar Plant Site 2 is a 47.3 MW solar power plant in Kern County, California, operated by Sune Beacon Site 2, LLC, and it generated 112,294 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in California, and its capacity factor sits at the 78th percentile of U.S. solar plants. By 2025 generation it ranks 3,279th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

47.3 MWNameplate capacity
27%Capacity factor, 2025, 78th percentile, on 47.3 MW net summer
0.1%Of CA generation, 2025
8 yearsAverage generator age, by MW

How hard does the Beacon Solar Plant Site 2 plant run compared with other solar plants?

The Beacon Solar Plant Site 2 plant had a capacity factor of 27% in 2025 on 47.3 MW of net summer capacity, the 78th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 99 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Beacon Solar Plant Site 227%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Beacon Solar Plant Site 2 plant generating more or less than last year?

Generation at Beacon Solar Plant Site 2 rose 2.2% from 2024 to 2025, from 109,859 MWh to 112,294 MWh. Through August 2026 it is running 11.6% behind the same months of 2025.

Net generation by period
PeriodMWh
2024109,859
2025112,294
2026 through August75,390
2025, same months85,265
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 20269,772
July 202611,448
June 202611,646
May 20269,755
April 202611,111
March 20269,134
February 20266,818
January 20265,706
December 20254,454
November 20254,814
October 20258,808
September 20258,953
August 202510,848
July 202513,107
June 202513,513
May 202513,550
April 202512,470
March 20258,615
February 20256,752
January 20256,410
December 20245,124
November 20246,291
October 20248,245
September 202410,289
August 202412,145
July 202412,079
June 202413,290
May 202413,368
April 202412,063
March 20249,687
February 2024886
January 20246,392

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Beacon Solar Plant Site 2 plant?

Beacon Solar Plant Site 2 made 0.1% of the 204,542,898 MWh reported by California plants in 2025, from 0.0% of the state's 107,433 MW of capacity. Its share of output is 1.2 times its share of capacity. By capacity it is the 457th largest of 1,877 plants in California, the 3,916th largest of 14,327 in the U.S. and the 939th largest of 7,223 solar plants. By 2025 generation it is the 342nd largest of 1,608 generating plants in the state.

Beacon Solar Plant Site 2 within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)47107,4330.0%
Generation (MWh)112,294204,542,8980.1%
Solar capacity (MW)4724,6630.2%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Beacon Solar Plant Site 2 plant, and when do they retire?

1 operable generator totals 47.3 MW, with an average age of 8 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s147100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
BEAC2OperatingSolar Photovoltaic472017n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Beacon Solar Plant Site 2 plant?

EIA lists no joint owners for Beacon Solar Plant Site 2. Sune Beacon Site 2, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Beacon Solar Plant Site 2 plant?

Beacon Solar Plant Site 2 is in Cantil, Kern County, California, at 35.2658° N, 117.9992° W. It sits in the Los Angeles Department of Water and Power balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and Beacon Solar Plant Site 2's 47.3 MW is 0% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
Ocotillo WellsSan Diego50108,077
Baldy Mesa 2_Silver Peak HybridSan Bernardino50126,997
Resurgence Solar IISan Bernardino48140,345
Beacon Solar Plant Site 2Kern47112,294
RE Camelot LLCKern45121,010
RE Gaskell West 2 LLCKern45111,461
Edwards Sanborn S1Kern45103,431