Wind power plant, Iowa

Beaver Creek Wind power plant, Iowa

Beaver Creek Wind is a 340 MW wind power plant in Boone County, Iowa, operated by MidAmerican Energy Co, and it generated 1,258,157 MWh in 2025 (Forms EIA-860 and EIA-923). That is 1.7% of the generation reported in Iowa, and its capacity factor sits at the 83rd percentile of U.S. wind plants. By 2025 generation it ranks 649th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

340 MWNameplate capacity
42%Capacity factor, 2025, 83rd percentile, on 340 MW net summer
1.7%Of IA generation, 2025
8 yearsAverage generator age, by MW

How hard does the Beaver Creek Wind plant run compared with other wind plants?

The Beaver Creek Wind plant had a capacity factor of 42% in 2025 on 340 MW of net summer capacity, the 83rd percentile of the 1,031 U.S. wind plants with at least 20 MW. The typical wind plant reached 33%. That equals about 154 days at full output out of 365.

0%Shaded: the middle half of wind plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Beaver Creek Wind42%
Wind plants, 75th percentile41%
Wind plants, median33%
Wind plants, 25th percentile26%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Beaver Creek Wind plant generating more or less than last year?

Generation at Beaver Creek Wind fell 8.3% from 2024 to 2025, from 1,371,484 MWh to 1,258,157 MWh. Through August 2026 it is running 5.3% behind the same months of 2025.

Net generation by period
PeriodMWh
20241,371,484
20251,258,157
2026 through August815,908
2025, same months861,988
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202657,297
July 202647,537
June 202689,219
May 2026111,480
April 2026145,259
March 2026138,871
February 2026107,743
January 2026118,502
December 2025116,119
November 202579,828
October 2025132,145
September 202568,077
August 202556,674
July 202558,376
June 202584,921
May 202598,130
April 2025152,284
March 2025142,963
February 2025128,298
January 2025140,342
December 2024113,427
November 2024124,617
October 2024138,358
September 202487,212
August 202468,430
July 202453,097
June 2024106,525
May 2024118,241
April 2024164,882
March 2024164,005
February 2024128,448
January 2024104,242

Source: EIA Form EIA-923, through August 2026.

How much of Iowa's electricity comes from the Beaver Creek Wind plant?

Beaver Creek Wind made 1.7% of the 74,502,373 MWh reported by Iowa plants in 2025, from 1.4% of the state's 24,817 MW of capacity. Its share of output is 1.2 times its share of capacity. By capacity it is the 12th largest of 306 plants in Iowa, the 950th largest of 14,327 in the U.S. and the 39th largest of 1,358 wind plants. By 2025 generation it is the 14th largest of 283 generating plants in the state.

Beaver Creek Wind within Iowa, 2025
MeasureThis plantIowaShare
Capacity (MW)34024,8171.4%
Generation (MWh)1,258,15774,502,3731.7%
Wind capacity (MW)34013,4102.5%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Beaver Creek Wind plant, and when do they retire?

2 operable generators total 340 MW, with an average age of 8 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s2340100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
1OperatingOnshore Wind Turbine1702017n/a
GT1OperatingOnshore Wind Turbine1702018n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Beaver Creek Wind plant?

EIA lists no joint owners for Beaver Creek Wind. MidAmerican Energy Co operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

What does MidAmerican Energy Co charge homes?

MidAmerican Energy Co, the operator of Beaver Creek Wind, had an average residential price of 11.21¢ per kWh and an average bill of $93 a month in 2025, 18% below the Iowa average of 13.62¢.

Average residential price and bill, 2025
MeasurePriceMonthly billAgainst Iowa
MidAmerican Energy Co11.21¢$9318% lower
Iowa average13.62¢$117
U.S. average17.23¢$15126% higher

Source: EIA Form EIA-861, final 2025. Average price is revenue divided by sales. It is what the seller's customers paid on average, not the cost of this plant's output.

Where is the Beaver Creek Wind plant?

Beaver Creek Wind is in Ogden, Boone County, Iowa, at 42.1070° N, 94.1646° W. It sits in the Midcontinent Independent Transmission System Operator, Inc. balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which wind plants in Iowa are similar in size?

Iowa has 123 operable wind plants with 13,410 MW of capacity, and Beaver Creek Wind's 340 MW is 3% of that.

Wind plants in Iowa around this size
PlantCountyMW2025 MWh
Highland Wind Project (IA)O'Brien5021,554,390
Orient Wind FarmAdair5011,819,787
Rolling Hills Wind FarmCass4841,577,482
Beaver Creek WindBoone3401,258,157
North EnglishPoweshiek3401,320,788
Palo Alto Wind FarmPalo Alto3401,454,330
Arbor Hill Wind FarmAdair3101,148,002