Solar power plant, Virginia

Carvers Creek Solar power plant, Virginia

Carvers Creek Solar is a 154 MW solar power plant in Gloucester County, Virginia, operated by Carvers Creek, LLC, and it generated 223,997 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Virginia, and its capacity factor sits at the 14th percentile of U.S. solar plants. By 2025 generation it ranks 2,350th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

154 MWNameplate capacity
17%Capacity factor, 2025, 14th percentile, on 154 MW net summer
0.2%Of VA generation, 2025
Under 1 yearAverage generator age, by MW

How hard does the Carvers Creek Solar plant run compared with other solar plants?

The Carvers Creek Solar plant had a capacity factor of 17% in 2025 on 154 MW of net summer capacity, the 14th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 61 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Carvers Creek Solar17%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Carvers Creek Solar plant generating more or less than last year?

Carvers Creek Solar generated 223,997 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 32.4% ahead of the same months of 2025. 2024 has output for only 5 months, so the two years are not compared.

Net generation by period
PeriodMWh
202434,675
2025223,997
2026 through August221,551
2025, same months167,393
Monthly generation, Aug 2024 to Aug 2026
MonthMWh
August 202633,893
July 202632,761
June 202636,878
May 202632,353
April 202630,765
March 202622,461
February 202617,138
January 202615,302
December 202510,277
November 202511,558
October 202517,807
September 202516,962
August 202522,395
July 202525,511
June 202525,476
May 202521,429
April 202522,298
March 202522,559
February 202514,411
January 202513,314
December 20248,661
November 20243,427
October 20249,417
September 20246,267
August 20246,903

Source: EIA Form EIA-923, through August 2026.

How much of Virginia's electricity comes from the Carvers Creek Solar plant?

Carvers Creek Solar made 0.2% of the 106,220,859 MWh reported by Virginia plants in 2025, from 0.5% of the state's 31,312 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 34th largest of 259 plants in Virginia, the 1,940th largest of 14,327 in the U.S. and the 251st largest of 7,223 solar plants. By 2025 generation it is the 39th largest of 241 generating plants in the state.

Carvers Creek Solar within Virginia, 2025
MeasureThis plantVirginiaShare
Capacity (MW)15431,3120.5%
Generation (MWh)223,997106,220,8590.2%
Solar capacity (MW)1545,1633.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Carvers Creek Solar plant, and when do they retire?

2 operable generators total 154 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s2154100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
CARVOperatingSolar Photovoltaic552024n/a
CARV2OperatingSolar Photovoltaic992025n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Carvers Creek Solar plant?

EIA lists no joint owners for Carvers Creek Solar. Carvers Creek, LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Carvers Creek Solar plant?

Carvers Creek Solar is in Gloucester, Gloucester County, Virginia, at 37.5619° N, 76.6054° W. It sits in the PJM Interconnection, LLC balancing area (NERC region SERC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Virginia are similar in size?

Virginia has 141 operable solar plants with 5,163 MW of capacity, and Carvers Creek Solar's 154 MW is 3% of that.

Solar plants in Virginia around this size
PlantCountyMW2025 MWh
Skipjack Solar CenterCharles City175298,427
Highlander Solar Energy Station 1Spotsylvania165286,818
Cavalier SolarIsle of Wight156301,761
Carvers Creek SolarGloucester154223,997
Fort Powhatan SolarPrince George150306,961
Spring Grove Solar 2Surry1505,048
Colonial Trail WestSurry142283,404

Source: EIA Forms EIA-860 and EIA-923, 2025.