Solar power plant, Virginia
Cavalier Solar power plant, Virginia
Cavalier Solar is a 156 MW solar power plant in Isle of Wight County, Virginia, operated by AES Clean Energy, and it generated 301,761 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in Virginia, and its capacity factor sits at the 42nd percentile of U.S. solar plants. By 2025 generation it ranks 1,964th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Cavalier Solar plant run compared with other solar plants?
The Cavalier Solar plant had a capacity factor of 22% in 2025 on 156 MW of net summer capacity, the 42nd percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 81 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Cavalier Solar | 22% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Cavalier Solar plant generating more or less than last year?
Cavalier Solar generated 301,761 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 4.9% behind the same months of 2025. 2024 has output for only 7 months, so the two years are not compared.
| Period | MWh |
|---|---|
| 2024 | 179,758 |
| 2025 | 301,761 |
| 2026 through August | 215,497 |
| 2025, same months | 226,535 |
Monthly generation, Jun 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 29,334 |
| July 2026 | 28,188 |
| June 2026 | 34,407 |
| May 2026 | 33,862 |
| April 2026 | 32,623 |
| March 2026 | 25,582 |
| February 2026 | 16,657 |
| January 2026 | 14,844 |
| December 2025 | 12,155 |
| November 2025 | 18,253 |
| October 2025 | 22,750 |
| September 2025 | 22,068 |
| August 2025 | 27,666 |
| July 2025 | 32,822 |
| June 2025 | 33,639 |
| May 2025 | 25,374 |
| April 2025 | 33,009 |
| March 2025 | 28,625 |
| February 2025 | 17,593 |
| January 2025 | 27,807 |
| December 2024 | 21,830 |
| November 2024 | 12,236 |
| October 2024 | 36,936 |
| September 2024 | 15,061 |
| August 2024 | 30,678 |
| July 2024 | 24,333 |
| June 2024 | 38,684 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Cavalier Solar plant, and when do they retire?
1 operable generator totals 156 MW, with an average age of 1 year weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 156 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| CAVPV | Operating | Solar Photovoltaic | 156 | 2024 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Cavalier Solar plant?
EIA lists no joint owners for Cavalier Solar. AES Clean Energy operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Cavalier Solar plant?
Cavalier Solar is in Smithfield, Isle of Wight County, Virginia, at 37.0180° N, 76.7358° W. It sits in the PJM Interconnection, LLC balancing area (NERC region SERC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Virginia are similar in size?
Virginia has 141 operable solar plants with 5,163 MW of capacity, and Cavalier Solar's 156 MW is 3% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Pleinmont Solar 2 | Spotsylvania | 240 | 437,148 |
| Skipjack Solar Center | Charles City | 175 | 298,427 |
| Highlander Solar Energy Station 1 | Spotsylvania | 165 | 286,818 |
| Cavalier Solar | Isle of Wight | 156 | 301,761 |
| Carvers Creek Solar | Gloucester | 154 | 223,997 |
| Fort Powhatan Solar | Prince George | 150 | 306,961 |
| Spring Grove Solar 2 | Surry | 150 | 5,048 |
Source: EIA Forms EIA-860 and EIA-923, 2025.