Solar power plant, New Mexico

Chaves Solar, LLC power plant, New Mexico

Chaves Solar, LLC is a 70 MW solar power plant in Chaves County, New Mexico, operated by Chaves Solar LLC, and it generated 154,745 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.4% of the generation reported in New Mexico, and its capacity factor sits at the 66th percentile of U.S. solar plants. By 2025 generation it ranks 2,853rd of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

70 MWNameplate capacity
25%Capacity factor, 2025, 66th percentile, on 70 MW net summer
0.4%Of NM generation, 2025
9 yearsAverage generator age, by MW

How hard does the Chaves Solar, LLC plant run compared with other solar plants?

The Chaves Solar, LLC plant had a capacity factor of 25% in 2025 on 70 MW of net summer capacity, the 66th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 92 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Chaves Solar, LLC25%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Chaves Solar, LLC plant generating more or less than last year?

Generation at Chaves Solar, LLC rose 11.4% from 2024 to 2025, from 138,868 MWh to 154,745 MWh. Through August 2026 it is running 9.6% behind the same months of 2025.

Net generation by period
PeriodMWh
2024138,868
2025154,745
2026 through August102,121
2025, same months112,965
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202618,978
July 202619,138
June 202615,402
May 202613,101
April 20269,523
March 202610,244
February 20268,884
January 20266,851
December 20257,332
November 20258,921
October 202511,607
September 202513,920
August 202516,208
July 202517,679
June 202515,204
May 202516,931
April 202513,279
March 202512,631
February 202510,823
January 202510,210
December 20249,357
November 20247,381
October 202412,525
September 202414,224
August 202415,404
July 202415,850
June 202414,744
May 202414,917
April 20249,365
March 202410,319
February 20247,420
January 20247,362

Source: EIA Form EIA-923, through August 2026.

How much of New Mexico's electricity comes from the Chaves Solar, LLC plant?

Chaves Solar, LLC made 0.4% of the 39,178,246 MWh reported by New Mexico plants in 2025, from 0.5% of the state's 13,801 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 45th largest of 161 plants in New Mexico, the 3,346th largest of 14,327 in the U.S. and the 765th largest of 7,223 solar plants. By 2025 generation it is the 41st largest of 151 generating plants in the state.

Chaves Solar, LLC within New Mexico, 2025
MeasureThis plantNew MexicoShare
Capacity (MW)7013,8010.5%
Generation (MWh)154,74539,178,2460.4%
Solar capacity (MW)702,9022.4%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Chaves Solar, LLC plant, and when do they retire?

1 operable generator totals 70 MW, with an average age of 9 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s170100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
CSPVOperatingSolar Photovoltaic702016n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Chaves Solar, LLC plant?

EIA lists no joint owners for Chaves Solar, LLC. Chaves Solar LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Chaves Solar, LLC plant?

Chaves Solar, LLC is in Roswell, Chaves County, New Mexico, at 33.4500° N, 104.4560° W. It sits in the Southwest Power Pool balancing area (NERC region MRO).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in New Mexico are similar in size?

New Mexico has 101 operable solar plants with 2,902 MW of capacity, and Chaves Solar, LLC's 70 MW is 2% of that.

Solar plants in New Mexico around this size
PlantCountyMW2025 MWh
Shallow BasketRio Arriba140140,104
Buena Vista Energy CenterOtero120391,039
Quail Ranch Solar and BESSBernalillo10031,455
Chaves Solar, LLCChaves70154,745
Roswell Solar, LLCChaves70153,135
Macho SpringsLuna55124,218
Encino Solar Energy CenterSandoval55142,990

Source: EIA Forms EIA-860 and EIA-923, 2025.