Solar power plant, New Mexico
Macho Springs solar power plant, New Mexico
Macho Springs is a 55 MW solar power plant in Luna County, New Mexico, operated by Southern Power Co, and it generated 124,218 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in New Mexico, and its capacity factor sits at the 78th percentile of U.S. solar plants. By 2025 generation it ranks 3,156th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Macho Springs plant run compared with other solar plants?
The Macho Springs plant had a capacity factor of 27% in 2025 on 52.2 MW of net summer capacity, the 78th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 99 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Macho Springs | 27% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Macho Springs plant generating more or less than last year?
Generation at Macho Springs rose 1.3% from 2024 to 2025, from 122,680 MWh to 124,218 MWh.
| Period | MWh |
|---|---|
| 2024 | 122,680 |
| 2025 | 124,218 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 6,745 |
| November 2025 | 7,970 |
| October 2025 | 9,857 |
| September 2025 | 9,706 |
| August 2025 | 11,189 |
| July 2025 | 11,684 |
| June 2025 | 12,947 |
| May 2025 | 14,240 |
| April 2025 | 12,914 |
| March 2025 | 10,581 |
| February 2025 | 8,892 |
| January 2025 | 7,493 |
| December 2024 | 7,054 |
| November 2024 | 8,043 |
| October 2024 | 10,864 |
| September 2024 | 12,676 |
| August 2024 | 12,976 |
| July 2024 | 13,607 |
| June 2024 | 12,607 |
| May 2024 | 13,743 |
| April 2024 | 10,694 |
| March 2024 | 9,030 |
| February 2024 | 6,475 |
| January 2024 | 4,911 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Macho Springs plant, and when do they retire?
1 operable generator totals 55 MW, with an average age of 11 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 55 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| MSS1 | Operating | Solar Photovoltaic | 55 | 2014 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Macho Springs plant?
Macho Springs Solar, LLC is the only joint owner reported for Macho Springs, with 100.0%. Southern Power Co operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Macho Springs plant?
Macho Springs is in Deming, Luna County, New Mexico, at 32.5700° N, 107.4800° W. It sits in the El Paso Electric Company balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in New Mexico are similar in size?
New Mexico has 101 operable solar plants with 2,902 MW of capacity, and Macho Springs' 55 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Quail Ranch Solar and BESS | Bernalillo | 100 | 31,455 |
| Chaves Solar, LLC | Chaves | 70 | 154,745 |
| Roswell Solar, LLC | Chaves | 70 | 153,135 |
| Macho Springs | Luna | 55 | 124,218 |
| Encino Solar Energy Center | Sandoval | 55 | 142,990 |
| Britton Solar Energy Center | Torrance | 50 | 140,936 |
| Jicarilla Solar 2 | Rio Arriba | 50 | 127,578 |
Source: EIA Forms EIA-860 and EIA-923, 2025.