Skip to main content
RateWatt

Solar power plant, California

Genesis Solar Energy Project, California

Genesis Solar Energy Project is a 250 MW solar power plant in Riverside County, California, operated by Genesis Solar LLC, and it generated 607,891 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in California, and its capacity factor sits at the 81st percentile of U.S. solar plants. By 2025 generation it ranks 1,118th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

250 MWNameplate capacity
28%Capacity factor, 2025, 81st percentile, on 250 MW net summer
0.3%Of CA generation, 2025
12 yearsAverage generator age, by MW

How hard does the Genesis Solar Energy Project plant run compared with other solar plants?

The Genesis Solar Energy Project plant had a capacity factor of 28% in 2025 on 250 MW of net summer capacity, the 81st percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 101 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Genesis Solar Energy Project28%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Genesis Solar Energy Project plant generating more or less than last year?

Generation at Genesis Solar Energy Project fell 2.5% from 2024 to 2025, from 623,699 MWh to 607,891 MWh. Through August 2026 it is running 5.8% behind the same months of 2025.

Net generation by period
PeriodMWh
2024623,699
2025607,891
2026 through August433,717
2025, same months460,511
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202659,818
July 202665,020
June 202676,771
May 202678,921
April 202656,355
March 202654,982
February 202629,761
January 202612,089
December 202519,238
November 202525,843
October 202551,179
September 202551,120
August 202567,315
July 202576,449
June 202576,711
May 202571,336
April 202567,768
March 202550,367
February 202544,616
January 20255,949
December 202431,086
November 202431,085
October 202449,184
September 202463,708
August 202466,545
July 202473,400
June 202479,534
May 202481,067
April 202466,029
March 202453,182
February 202424,675
January 20244,204

Source: EIA Form EIA-923, through August 2026.

How much of California's electricity comes from the Genesis Solar Energy Project plant?

Genesis Solar Energy Project made 0.3% of the 204,542,898 MWh reported by California plants in 2025, from 0.2% of the state's 107,433 MW of capacity. Its share of output is 1.3 times its share of capacity. By capacity it is the 100th largest of 1,877 plants in California, the 1,239th largest of 14,327 in the U.S. and the 80th largest of 7,223 solar plants. By 2025 generation it is the 61st largest of 1,608 generating plants in the state.

Genesis Solar Energy Project within California, 2025
MeasureThis plantCaliforniaShare
Capacity (MW)250107,4330.2%
Generation (MWh)607,891204,542,8980.3%
Solar capacity (MW)25024,6631.0%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Genesis Solar Energy Project plant, and when do they retire?

2 operable generators total 250 MW, with an average age of 12 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2010s2250100%none reported
Every generator, 2 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GEN02OperatingSolar Thermal without Energy Storage1252013n/a
GEN01OperatingSolar Thermal without Energy Storage1252014n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Genesis Solar Energy Project plant?

EIA lists no joint owners for Genesis Solar Energy Project. Genesis Solar LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Genesis Solar Energy Project plant?

Genesis Solar Energy Project is in Blythe, Riverside County, California, at 33.6650° N, 114.9981° W. It sits in the California Independent System Operator balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in California are similar in size?

California has 934 operable solar plants with 24,663 MW of capacity, and Genesis Solar Energy Project's 250 MW is 1% of that.

Solar plants in California around this size
PlantCountyMW2025 MWh
Arica SolarRiverside263811,170
AV Solar Ranch OneLos Angeles253564,815
Mount Signal Solar Farm VImperial252674,337
Genesis Solar Energy ProjectRiverside250607,891
AquamarineKings250662,406
Athos Solar ProjectRiverside250700,249
Solar BlueKings250691,363

Source: EIA Forms EIA-860 and EIA-923, 2025.