Athos Solar Project is a 250 MW solar power plant in Riverside County, California, operated by SE Athos I, LLC, and it generated 700,249 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in California, and its capacity factor sits at the 96th percentile of U.S. solar plants. By 2025 generation it ranks 990th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Athos Solar Project plant run compared with other solar plants?
The Athos Solar Project plant had a capacity factor of 32% in 2025 on 250 MW of net summer capacity, the 96th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 117 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Athos Solar Project | 32% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Athos Solar Project plant generating more or less than last year?
Generation at Athos Solar Project rose 13.3% from 2024 to 2025, from 618,067 MWh to 700,249 MWh. Through August 2026 it is running 6.0% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 618,067 |
| 2025 | 700,249 |
| 2026 through August | 469,620 |
| 2025, same months | 499,384 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 72,167 |
| July 2026 | 66,525 |
| June 2026 | 72,340 |
| May 2026 | 80,774 |
| April 2026 | 51,424 |
| March 2026 | 47,945 |
| February 2026 | 37,170 |
| January 2026 | 41,275 |
| December 2025 | 37,613 |
| November 2025 | 41,946 |
| October 2025 | 60,419 |
| September 2025 | 60,887 |
| August 2025 | 76,642 |
| July 2025 | 83,610 |
| June 2025 | 83,706 |
| May 2025 | 72,402 |
| April 2025 | 69,164 |
| March 2025 | 34,774 |
| February 2025 | 35,824 |
| January 2025 | 43,262 |
| December 2024 | 39,561 |
| November 2024 | 46,776 |
| October 2024 | 56,718 |
| September 2024 | 66,708 |
| August 2024 | 78,483 |
| July 2024 | 82,544 |
| June 2024 | 79,954 |
| May 2024 | 51,639 |
| April 2024 | 29,187 |
| March 2024 | 20,203 |
| February 2024 | 35,828 |
| January 2024 | 30,466 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Athos Solar Project plant, and when do they retire?
1 operable generator totals 250 MW, with an average age of 3 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 250 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| IPAT1 | Operating | Solar Photovoltaic | 250 | 2022 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Athos Solar Project plant?
EIA lists no joint owners for Athos Solar Project. SE Athos I, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Athos Solar Project plant?
Athos Solar Project is in Desert Center, Riverside County, California, at 33.7513° N, 115.3550° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and Athos Solar Project's 250 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Mount Signal Solar Farm V | Imperial | 252 | 674,337 |
| Genesis Solar Energy Project | Riverside | 250 | 607,891 |
| Aquamarine | Kings | 250 | 662,406 |
| Athos Solar Project | Riverside | 250 | 700,249 |
| Solar Blue | Kings | 250 | 691,363 |
| Oberon Solar Project | Riverside | 250 | 599,752 |
| Oberon II Solar Project | Riverside | 250 | 607,785 |
Source: EIA Forms EIA-860 and EIA-923, 2025.