Great Bend Solar Project is a 48 MW solar power plant in Meigs County, Ohio, operated by Great Bend Solar LLC, and it generated 2,654 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 1st percentile of U.S. solar plants. By 2025 generation it ranks 10,026th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

48 MWNameplate capacity
under 1%Capacity factor, 2025, 1st percentile, on 48 MW net summer
10,026thU.S. rank by generation, 2025
Under 1 yearAverage generator age, by MW

How hard does the Great Bend Solar Project plant run compared with other solar plants?

The Great Bend Solar Project plant had a capacity factor of under 1% in 2025 on 48 MW of net summer capacity, the 1st percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. It ran for only a few hours of the year at full output.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
Great Bend Solar Projectunder 1%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the Great Bend Solar Project plant generating more or less than last year?

Great Bend Solar Project generated 2,654 MWh in 2025; EIA reports no 2024 total to compare.

Net generation by period
PeriodMWh
2024n/a
20252,654
2026 through August70,710
Monthly generation, Dec 2025 to Aug 2026
MonthMWh
August 202610,363
July 202611,053
June 202610,930
May 202610,500
April 202610,633
March 20267,217
February 20265,683
January 20264,331
December 20252,654

Source: EIA Form EIA-923, through August 2026.

How much of Ohio's electricity comes from the Great Bend Solar Project plant?

Great Bend Solar Project made 0.0% of the 145,060,499 MWh reported by Ohio plants in 2025, from 0.1% of the state's 34,392 MW of capacity. Its share of output is smaller than its share of capacity. By capacity it is the 76th largest of 215 plants in Ohio, the 3,894th largest of 14,327 in the U.S. and the 937th largest of 7,223 solar plants. By 2025 generation it is the 115th largest of 187 generating plants in the state.

Great Bend Solar Project within Ohio, 2025
MeasureThis plantOhioShare
Capacity (MW)4834,3920.1%
Generation (MWh)2,654145,060,4990.0%
Solar capacity (MW)484,4811.1%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the Great Bend Solar Project plant, and when do they retire?

1 operable generator totals 48 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s148100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
GBSP1OperatingSolar Photovoltaic482025n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the Great Bend Solar Project plant?

EIA lists no joint owners for Great Bend Solar Project. Great Bend Solar LLC operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the Great Bend Solar Project plant?

Great Bend Solar Project is in Portland, Meigs County, Ohio, at 39.0033° N, 81.7711° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in Ohio are similar in size?

Ohio has 73 operable solar plants with 4,481 MW of capacity, and Great Bend Solar Project's 48 MW is 1% of that.

Solar plants in Ohio around this size
PlantCountyMW2025 MWh
Blue Harvest Solar ParkPutnam5099,534
Timber Road Solar ParkPaulding5099,640
Clinton Solar (OH)Clinton505,038
Great Bend Solar ProjectMeigs482,654
Fayette SolarRoss4588,928

Source: EIA Forms EIA-860 and EIA-923, 2025.