Solar power plant, Arizona
Kayenta Solar Project, Arizona
Kayenta Solar Project is a 55.3 MW solar power plant in Navajo County, Arizona, operated by NGI-Kayenta Solar Lessor I, LLC, and it generated 121,046 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.1% of the generation reported in Arizona, and its capacity factor sits at the 64th percentile of U.S. solar plants. By 2025 generation it ranks 3,183rd of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Kayenta Solar Project plant run compared with other solar plants?
The Kayenta Solar Project plant had a capacity factor of 25% in 2025 on 55.3 MW of net summer capacity, the 64th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 91 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Kayenta Solar Project | 25% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Kayenta Solar Project plant generating more or less than last year?
Generation at Kayenta Solar Project rose 38.3% from 2024 to 2025, from 87,547 MWh to 121,046 MWh. Through August 2026 it is running 1.7% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 87,547 |
| 2025 | 121,046 |
| 2026 through August | 88,203 |
| 2025, same months | 89,764 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 10,962 |
| July 2026 | 11,706 |
| June 2026 | 13,277 |
| May 2026 | 13,856 |
| April 2026 | 12,374 |
| March 2026 | 11,742 |
| February 2026 | 7,654 |
| January 2026 | 6,632 |
| December 2025 | 5,728 |
| November 2025 | 6,511 |
| October 2025 | 9,360 |
| September 2025 | 9,683 |
| August 2025 | 11,659 |
| July 2025 | 12,339 |
| June 2025 | 13,414 |
| May 2025 | 14,165 |
| April 2025 | 12,780 |
| March 2025 | 10,684 |
| February 2025 | 8,104 |
| January 2025 | 6,619 |
| December 2024 | 6,157 |
| November 2024 | 6,131 |
| October 2024 | 5,497 |
| September 2024 | 7,416 |
| August 2024 | 8,377 |
| July 2024 | 8,788 |
| June 2024 | 9,258 |
| May 2024 | 10,902 |
| April 2024 | 8,462 |
| March 2024 | 7,354 |
| February 2024 | 4,839 |
| January 2024 | 4,366 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Kayenta Solar Project plant, and when do they retire?
2 operable generators total 55.3 MW, with an average age of 7 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 2 | 55 | 100% | none reported |
Every generator, 2 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| PV1 | Operating | Solar Photovoltaic | 27 | 2017 | n/a |
| PV2 | Operating | Solar Photovoltaic | 28 | 2019 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Kayenta Solar Project plant?
EIA lists no joint owners for Kayenta Solar Project. NGI-Kayenta Solar Lessor I, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Kayenta Solar Project plant?
Kayenta Solar Project is in Kayenta, Navajo County, Arizona, at 36.7719° N, 110.2639° W. It sits in the Western Area Power Administration - Desert Southwest Region balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Arizona are similar in size?
Arizona has 111 operable solar plants with 6,672 MW of capacity, and Kayenta Solar Project's 55.3 MW is 1% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| West Line Solar, LLC | Pinal | 100 | 258,633 |
| Yuma Solar + Storage | Yuma | 70 | 169,606 |
| Mesquite Solar 5, LLC | Maricopa | 60 | 143,619 |
| Kayenta Solar Project | Navajo | 55 | 121,046 |
| Gray Hawk Solar | Mohave | 55 | 136,815 |
| Mesquite Solar 4, LLC | Maricopa | 53 | 145,865 |
| Red Horse 2 | Cochise | 51 | 102,027 |
Source: EIA Forms EIA-860 and EIA-923, 2025.