Solar power plant, California
NextEra Westside PV solar power plant, California
NextEra Westside PV is a 20 MW solar power plant in Fresno County, California, operated by Westside Solar, LLC, and it generated 25,668 MWh in 2025 (Forms EIA-860 and EIA-923). Its capacity factor sits at the 12th percentile of U.S. solar plants. By 2025 generation it ranks 4,935th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the NextEra Westside PV plant run compared with other solar plants?
The NextEra Westside PV plant had a capacity factor of 15% in 2025 on 20 MW of net summer capacity, the 12th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 53 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| NextEra Westside PV | 15% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the NextEra Westside PV plant generating more or less than last year?
Generation at NextEra Westside PV fell 36.8% from 2024 to 2025, from 40,622 MWh to 25,668 MWh.
| Period | MWh |
|---|---|
| 2024 | 40,622 |
| 2025 | 25,668 |
Monthly generation, Jan 2024 to Dec 2025
| Month | MWh |
|---|---|
| December 2025 | 1,059 |
| November 2025 | 2,009 |
| October 2025 | 1,878 |
| September 2025 | 2,032 |
| August 2025 | 3,634 |
| July 2025 | 3,126 |
| June 2025 | 3,428 |
| May 2025 | 3,446 |
| April 2025 | 1,148 |
| March 2025 | 422 |
| February 2025 | 1,345 |
| January 2025 | 2,141 |
| December 2024 | 1,971 |
| November 2024 | 2,268 |
| October 2024 | 2,454 |
| September 2024 | 3,183 |
| August 2024 | 5,022 |
| July 2024 | 5,687 |
| June 2024 | 5,062 |
| May 2024 | 4,302 |
| April 2024 | 3,315 |
| March 2024 | 2,786 |
| February 2024 | 2,590 |
| January 2024 | 1,982 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the NextEra Westside PV plant, and when do they retire?
1 operable generator totals 20 MW, with an average age of 8 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2010s | 1 | 20 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| WS526 | Operating | Solar Photovoltaic | 20 | 2017 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the NextEra Westside PV plant?
EIA lists no joint owners for NextEra Westside PV. Westside Solar, LLC operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the NextEra Westside PV plant?
NextEra Westside PV is in Five Points, Fresno County, California, at 36.3818° N, 120.1345° W. It sits in the California Independent System Operator balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in California are similar in size?
California has 934 operable solar plants with 24,663 MW of capacity, and NextEra Westside PV's 20 MW is 0% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Solar Blythe 2 | Riverside | 20 | 40,700 |
| Jacumba Solar Farm | San Diego | 20 | 46,262 |
| Whitney Point Solar | Fresno | 20 | 54,152 |
| NextEra Westside PV | Fresno | 20 | 25,668 |
| Antelope DSR 3 | Los Angeles | 20 | 55,108 |
| Gaskell West 1 Solar Facility | Kern | 20 | 55,559 |
| RE Gaskell West 3 LLC | Kern | 20 | 50,755 |
Source: EIA Forms EIA-860 and EIA-923, 2025.