Solar power plant, New Mexico
NMRD Data Center III, LLC solar power plant, New Mexico
NMRD Data Center III, LLC is a 50 MW solar power plant in Sandoval County, New Mexico, operated by Exus New Mexico, and it generated 135,624 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in New Mexico, and its capacity factor sits at the 94th percentile of U.S. solar plants. By 2025 generation it ranks 3,049th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the NMRD Data Center III, LLC plant run compared with other solar plants?
The NMRD Data Center III, LLC plant had a capacity factor of 31% in 2025 on 50 MW of net summer capacity, the 94th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 113 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| NMRD Data Center III, LLC | 31% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the NMRD Data Center III, LLC plant generating more or less than last year?
Generation at NMRD Data Center III, LLC fell 1.2% from 2024 to 2025, from 137,282 MWh to 135,624 MWh. Through August 2026 it is running 6.3% behind the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | 137,282 |
| 2025 | 135,624 |
| 2026 through August | 93,467 |
| 2025, same months | 99,786 |
Monthly generation, Jan 2024 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 12,978 |
| July 2026 | 14,250 |
| June 2026 | 13,646 |
| May 2026 | 11,387 |
| April 2026 | 13,294 |
| March 2026 | 11,355 |
| February 2026 | 8,712 |
| January 2026 | 7,845 |
| December 2025 | 7,044 |
| November 2025 | 7,988 |
| October 2025 | 9,820 |
| September 2025 | 10,986 |
| August 2025 | 13,003 |
| July 2025 | 12,792 |
| June 2025 | 14,343 |
| May 2025 | 14,997 |
| April 2025 | 14,403 |
| March 2025 | 12,717 |
| February 2025 | 9,335 |
| January 2025 | 8,196 |
| December 2024 | 7,635 |
| November 2024 | 8,043 |
| October 2024 | 10,952 |
| September 2024 | 12,449 |
| August 2024 | 12,820 |
| July 2024 | 14,752 |
| June 2024 | 13,594 |
| May 2024 | 16,178 |
| April 2024 | 14,623 |
| March 2024 | 10,942 |
| February 2024 | 8,429 |
| January 2024 | 6,865 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the NMRD Data Center III, LLC plant, and when do they retire?
1 operable generator totals 50 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 50 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| NMRD3 | Operating | Solar Photovoltaic | 50 | 2023 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the NMRD Data Center III, LLC plant?
EIA lists no joint owners for NMRD Data Center III, LLC. Exus New Mexico operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the NMRD Data Center III, LLC plant?
NMRD Data Center III, LLC is in Rio Ranchero, Sandoval County, New Mexico, at 35.3709° N, 106.8540° W. It sits in the Public Service Company of New Mexico balancing area (NERC region WECC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in New Mexico are similar in size?
New Mexico has 101 operable solar plants with 2,902 MW of capacity, and NMRD Data Center III, LLC's 50 MW is 2% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Britton Solar Energy Center | Torrance | 50 | 140,936 |
| Jicarilla Solar 2 | Rio Arriba | 50 | 127,578 |
| Jicarilla Solar 1 LLC | Rio Arriba | 50 | 111,188 |
| NMRD Data Center III, LLC | Sandoval | 50 | 135,624 |
| Route 66 Energy Center, LLC | Cibola | 50 | 131,985 |
| Cimarron Solar Facility | Colfax | 31 | 60,272 |
| Chaves County Solar II | Chaves | 30 | 70,717 |
Source: EIA Forms EIA-860 and EIA-923, 2025.