Skip to main content
RateWatt

Solar power plant, New Mexico

NMRD Data Center III, LLC solar power plant, New Mexico

NMRD Data Center III, LLC is a 50 MW solar power plant in Sandoval County, New Mexico, operated by Exus New Mexico, and it generated 135,624 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.3% of the generation reported in New Mexico, and its capacity factor sits at the 94th percentile of U.S. solar plants. By 2025 generation it ranks 3,049th of 12,977 U.S. plants.

Latest data: August 2026; data loaded .

50 MWNameplate capacity
31%Capacity factor, 2025, 94th percentile, on 50 MW net summer
0.3%Of NM generation, 2025
2 yearsAverage generator age, by MW

How hard does the NMRD Data Center III, LLC plant run compared with other solar plants?

The NMRD Data Center III, LLC plant had a capacity factor of 31% in 2025 on 50 MW of net summer capacity, the 94th percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 113 days at full output out of 365.

0%Shaded: the middle half of solar plants. Mark: this plant.105%

Capacity factor, 2025
MeasureCapacity factor
NMRD Data Center III, LLC31%
Solar plants, 75th percentile27%
Solar plants, median23%
Solar plants, 25th percentile20%

Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.

Is the NMRD Data Center III, LLC plant generating more or less than last year?

Generation at NMRD Data Center III, LLC fell 1.2% from 2024 to 2025, from 137,282 MWh to 135,624 MWh. Through August 2026 it is running 6.3% behind the same months of 2025.

Net generation by period
PeriodMWh
2024137,282
2025135,624
2026 through August93,467
2025, same months99,786
Monthly generation, Jan 2024 to Aug 2026
MonthMWh
August 202612,978
July 202614,250
June 202613,646
May 202611,387
April 202613,294
March 202611,355
February 20268,712
January 20267,845
December 20257,044
November 20257,988
October 20259,820
September 202510,986
August 202513,003
July 202512,792
June 202514,343
May 202514,997
April 202514,403
March 202512,717
February 20259,335
January 20258,196
December 20247,635
November 20248,043
October 202410,952
September 202412,449
August 202412,820
July 202414,752
June 202413,594
May 202416,178
April 202414,623
March 202410,942
February 20248,429
January 20246,865

Source: EIA Form EIA-923, through August 2026.

How much of New Mexico's electricity comes from the NMRD Data Center III, LLC plant?

NMRD Data Center III, LLC made 0.3% of the 39,178,246 MWh reported by New Mexico plants in 2025, from 0.4% of the state's 13,801 MW of capacity. By capacity it is the 53rd largest of 161 plants in New Mexico, the 3,754th largest of 14,327 in the U.S. and the 907th largest of 7,223 solar plants. By 2025 generation it is the 47th largest of 151 generating plants in the state.

NMRD Data Center III, LLC within New Mexico, 2025
MeasureThis plantNew MexicoShare
Capacity (MW)5013,8010.4%
Generation (MWh)135,62439,178,2460.3%
Solar capacity (MW)502,9021.7%

Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.

How old are the generators at the NMRD Data Center III, LLC plant, and when do they retire?

1 operable generator totals 50 MW, with an average age of 2 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.

Operable generators by decade in service
Entered serviceUnitsMWSharePlanned retirement
2020s150100%none reported
Every generator, 1 in all
UnitStatusTechnologyMWIn servicePlanned retirement
NMRD3OperatingSolar Photovoltaic502023n/a

Source: EIA Form EIA-860, Generator, 2025 final.

Who owns the NMRD Data Center III, LLC plant?

EIA lists no joint owners for NMRD Data Center III, LLC. Exus New Mexico operates the plant.

Source: EIA Form EIA-860, Owner, 2025 final.

Where is the NMRD Data Center III, LLC plant?

NMRD Data Center III, LLC is in Rio Ranchero, Sandoval County, New Mexico, at 35.3709° N, 106.8540° W. It sits in the Public Service Company of New Mexico balancing area (NERC region WECC).

Source: EIA Form EIA-860, Plant, 2025 final.

Which solar plants in New Mexico are similar in size?

New Mexico has 101 operable solar plants with 2,902 MW of capacity, and NMRD Data Center III, LLC's 50 MW is 2% of that.

Solar plants in New Mexico around this size
PlantCountyMW2025 MWh
Britton Solar Energy CenterTorrance50140,936
Jicarilla Solar 2Rio Arriba50127,578
Jicarilla Solar 1 LLCRio Arriba50111,188
NMRD Data Center III, LLCSandoval50135,624
Route 66 Energy Center, LLCCibola50131,985
Cimarron Solar FacilityColfax3160,272
Chaves County Solar IIChaves3070,717

Source: EIA Forms EIA-860 and EIA-923, 2025.