Solar power plant, Ohio
Ross County Solar, LLC power plant, Ohio
Ross County Solar, LLC is a 120 MW solar power plant in Ross County, Ohio, operated by Geronimo Power, and it generated 218,630 MWh in 2025 (Forms EIA-860 and EIA-923). That is 0.2% of the generation reported in Ohio, and its capacity factor sits at the 31st percentile of U.S. solar plants. By 2025 generation it ranks 2,374th of 12,977 U.S. plants.
Latest data: August 2026; data loaded .
How hard does the Ross County Solar, LLC plant run compared with other solar plants?
The Ross County Solar, LLC plant had a capacity factor of 21% in 2025 on 120 MW of net summer capacity, the 31st percentile of the 1,298 U.S. solar plants with at least 20 MW. The typical solar plant reached 23%. That equals about 76 days at full output out of 365.
0%Shaded: the middle half of solar plants. Mark: this plant.105%
| Measure | Capacity factor |
|---|---|
| Ross County Solar, LLC | 21% |
| Solar plants, 75th percentile | 27% |
| Solar plants, median | 23% |
| Solar plants, 25th percentile | 20% |
Source: EIA Forms EIA-860 and EIA-923, 2025. Capacity factor is net generation divided by capacity times the hours in the year, using net summer capacity, as EIA does. Values above 105% are left out of the comparison.
Is the Ross County Solar, LLC plant generating more or less than last year?
Ross County Solar, LLC generated 218,630 MWh in 2025; EIA reports no 2024 total to compare. Through August 2026 it is running 3.6% ahead of the same months of 2025.
| Period | MWh |
|---|---|
| 2024 | n/a |
| 2025 | 218,630 |
| 2026 through August | 168,178 |
| 2025, same months | 162,256 |
Monthly generation, Jan 2025 to Aug 2026
| Month | MWh |
|---|---|
| August 2026 | 23,411 |
| July 2026 | 28,622 |
| June 2026 | 26,756 |
| May 2026 | 25,176 |
| April 2026 | 24,979 |
| March 2026 | 17,758 |
| February 2026 | 12,321 |
| January 2026 | 9,155 |
| December 2025 | 5,877 |
| November 2025 | 8,957 |
| October 2025 | 17,920 |
| September 2025 | 23,620 |
| August 2025 | 29,102 |
| July 2025 | 26,696 |
| June 2025 | 21,623 |
| May 2025 | 22,852 |
| April 2025 | 21,570 |
| March 2025 | 18,286 |
| February 2025 | 11,696 |
| January 2025 | 10,431 |
Source: EIA Form EIA-923, through August 2026.
Source: EIA Forms EIA-860 and EIA-923, 2025. State totals add up the plants in these forms, including net use by storage.
How old are the generators at the Ross County Solar, LLC plant, and when do they retire?
1 operable generator totals 120 MW, with an average age of 0 years weighted by capacity at the end of 2025. No operable generator has a planned retirement date on Form EIA-860.
| Entered service | Units | MW | Share | Planned retirement |
|---|---|---|---|---|
| 2020s | 1 | 120 | 100% | none reported |
Every generator, 1 in all
| Unit | Status | Technology | MW | In service | Planned retirement |
|---|---|---|---|---|---|
| ROSS | Operating | Solar Photovoltaic | 120 | 2025 | n/a |
Source: EIA Form EIA-860, Generator, 2025 final.
Who owns the Ross County Solar, LLC plant?
EIA lists no joint owners for Ross County Solar, LLC. Geronimo Power operates the plant.
Source: EIA Form EIA-860, Owner, 2025 final.
Where is the Ross County Solar, LLC plant?
Ross County Solar, LLC is in Greenfield, Ross County, Ohio, at 39.3259° N, 83.3528° W. It sits in the PJM Interconnection, LLC balancing area (NERC region RFC).
Source: EIA Form EIA-860, Plant, 2025 final.
Which solar plants in Ohio are similar in size?
Ohio has 73 operable solar plants with 4,481 MW of capacity, and Ross County Solar, LLC's 120 MW is 3% of that.
| Plant | County | MW | 2025 MWh |
|---|---|---|---|
| Powell Creek Solar | Putnam | 150 | 219,815 |
| Clearview Solar 1 | Champaign | 144 | 282,274 |
| Wheatsborough Solar | Erie | 125 | 86,073 |
| Ross County Solar, LLC | Ross | 120 | 218,630 |
| Dodson Creek Solar, LLC | Highland | 117 | 166,013 |
| Sycamore Creek Solar, LLC | Crawford | 117 | 23,600 |
| Arche Energy Project, LLC | Fulton | 107 | 192,647 |
Source: EIA Forms EIA-860 and EIA-923, 2025.